Godawari Power & Ispat (GPIL) Q2 26/27 earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Godawari Power & Ispat Ltd

Q2 26/27 earnings summary

13 Nov, 2026

Executive summary

  • Q2 FY27 revenue increased YoY on both standalone and consolidated bases, while profit declined; the board approved substantial investment in energy storage, manufacturing capacity and power sourcing.

  • Strategic approvals include a 3 GWh C&I BESS project, a container manufacturing line, a relocated Cold Rolling Mill and renewable-power investment.

Financial highlights

  • Standalone Q2 revenue was Rs 1,410.53 crore vs Rs 1,142.57 crore YoY; PAT was Rs 102.19 crore vs Rs 248.40 crore, and PBT before exceptional items was Rs 132.88 crore vs Rs 312.96 crore.

  • Standalone H1 revenue was Rs 2,897.19 crore vs Rs 2,276.50 crore; PAT was Rs 301.09 crore vs Rs 448.90 crore YoY.

  • Consolidated Q2 revenue was Rs 1,631.53 crore vs Rs 1,307.68 crore YoY; net profit was Rs 85.00 crore vs Rs 161.65 crore, with a Rs 22.33 crore exceptional charge in Q2 FY27.

  • Consolidated H1 revenue was Rs 3,382.00 crore vs Rs 2,630.93 crore; net profit was Rs 307.37 crore vs Rs 378.05 crore YoY.

Outlook and guidance

  • The 3 GWh C&I BESS project is planned for construction from March 2027, subject to regulatory approvals, with commissioning targeted by March 2028.

  • The container line is planned alongside the CRM project at AURIC, Bidkin; the board announcement targets March 2028 commissioning, while Annexure D lists March 2027 tentatively.

  • The CRM project was relocated from Sarora, Chhattisgarh, to AURIC, Bidkin, Maharashtra, with revised project cost of Rs 1,100 crore including land and working-capital margin.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Godawari Power & Ispat