30 Oct, 2026Executive summary
9MFY2025 loss before tax widened to $7.65m from $0.94m, mainly due to negative property revenue from project cost revisions and LAD provisions.
Stronger metrology demand partly offset property weakness; cash and bank balances reached $19.56m at 31 March 2025.
Financial highlights
9MFY2025 revenue fell 63.1% YoY to $5.85m; gross profit was negative $3.08m versus positive $3.60m.
9MFY2025 loss before tax was $7.65m versus $0.94m; net loss was $7.96m versus $1.46m, including discontinued operations.
9MFY2025 basic and diluted loss per share was 2.968 cents versus 0.660 cents; no dividend was declared.
3QFY2025 revenue was negative $3.90m versus positive $4.80m; loss before tax was $8.15m versus $0.65m.
Outlook and guidance
Phase 1 and 2 of the Perak affordable housing project are targeted for completion by June 2026; Phase 3 is to follow, with total project cost expected to overrun.
Remaining PRC authority refund of RMB14.55m (~$2.71m) is expected to be recovered by 31 December 2025, based on the authority's 2025 budget assurance.
Latest events from GRP
- Revenue declined, but property work resumed with Phases 1 and 2 targeted for March 2026.BLU
AGM 2025 presentation - Revenue surged, losses narrowed, and affordable-housing projects progressed toward completion.BLU
AGM 2026 presentation - Revenue grew 23%, but lower gross profit and a wider pretax loss kept results under pressure.BLU
Q3 2024 - Losses narrowed, but a contractor dispute delayed the affordable housing project.BLU
AGM 2024 presentation - Continuing losses narrowed, but housing delays and audit qualifications remain.BLU
H2 2024 - Metrology growth and stronger cash offset property delays and a quarterly net loss.BLU
Q1 2025 - Profit returned as metrology gains offset property weakness and project delays.BLU
H1 2025 - Project delays and cost revisions drove a $8.79m FY2025 loss; housing completion targets extend to 2026.BLU
H2 2025 - Revenue grew 11.6%, but pretax profit dropped to S$62k amid housing project costs.BLU
H1 2026