Gruvaktiebolaget Viscaria (VISC) Q2 2024 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2024 earnings summary
13 Jun, 2025Executive summary
Environmental permit granted in May 2024 enables key project milestones and high-paced mine reopening; construction of a new water treatment plant began August 1.
Name changed to Gruvaktiebolaget Viscaria in May 2024; high activity in preparations and profitability study.
Plan to reopen Viscaria mine in 2026 remains unchanged, targeting 30,000 tons copper/year.
Assets increased from 52 to 93 million tons since 2020 through successful exploration.
Land allocation for the Viscaria project confirmed by court, reducing compensation to stakeholders and clearing path for development.
Financial highlights
Q2 2024 operating loss of -11 MSEK (Q2 2023: -8 MSEK); H1 2024 operating loss of -22 MSEK (H1 2023: -15 MSEK).
Q2 2024 net loss of -12 MSEK (Q2 2023: -9 MSEK); H1 2024 net loss of -23.5 MSEK (H1 2023: -15.9 MSEK).
Net sales were 0 MSEK for both Q2 and H1 2024, unchanged from previous periods.
Cash flow for Q2 2024 was 317 MSEK, up from 186 MSEK in Q2 2023, mainly from share issue.
Equity increased to 1,623 MSEK at Q2 2024 from 1,242 MSEK at Q2 2023.
Outlook and guidance
Focus for 2024 is on completing permitting, preparing for rapid restart, and finalizing the feasibility study by year-end.
Financing of 440 MSEK secured to support ongoing activities.
Environmental permit implementation began August 1, 2024; production start remains on track for 2026.
Solid financial position with 514 MSEK in cash; long-term debt expected to finance up to 60% of future investments.
Short-term copper price and FX volatility not expected to impact ongoing preparations.
Latest events from Gruvaktiebolaget Viscaria
- Permits, financing, and exploration success set stage for production ramp-up and 2027 mining start.VISC
Q4 202510 Feb 2026 - Permitted, low-cost copper project with strong growth, ESG profile, and robust financials.VISC
SEB Nordic Seminar presentation20 Jan 2026 - Permitted Swedish copper project targets 2027 production, leveraging rapid resource growth.VISC
ABGSC Investor Days9 Dec 2025 - Secured major financing and advanced toward 2027 production amid strong copper market conditions.VISC
Q3 20256 Nov 2025 - Permits, feasibility, and financing drive copper project toward profitable restart.VISC
Q2 202520 Aug 2025 - High-grade copper finds and permit progress drive strong outlook for 2026 reopening.VISC
Q3 202413 Jun 2025 - Viscaria advances with higher resources, strong economics, and major exploration upside.VISC
ABGSC Investor Days6 Jun 2025 - Environmental permit secured and copper resources up, project advances with strong economics.VISC
Q1 20256 Jun 2025 - Restart advanced, funding secured, and feasibility study due May 2025.VISC
Q4 20245 Jun 2025