Hibiya Engineering (1982) Q4 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2025 earnings summary
26 Oct, 2026Executive summary
FY3/25 net sales rose 7.2% YoY to ¥89,786m; operating profit increased 30.0% to ¥7,456m and parent-attributable profit grew 23.0% to ¥5,906m.
Results exceeded initial profit forecasts; sales missed the ¥91,000m forecast amid delays in some large projects, while orders of ¥93,655m exceeded the ¥88,500m forecast.
Strong data-center demand and improved project profitability supported earnings and kept carried-over projects at ¥85.6bn, up from ¥81.7bn in FY3/24.
Financial highlights
Gross profit rose to ¥17,266m from ¥14,903m; gross margin improved to 19.2% from 17.8%, while SG&A increased to ¥9,809m from ¥9,165m.
Ordinary profit increased 26.2% to ¥8,138m; parent-attributable profit reached ¥5,906m, including ¥596m gain on investment securities sales.
Total assets increased ¥1,689m to ¥99,915m; net assets rose ¥1,769m to ¥71,684m and the equity ratio improved to 70.6% from 70.0%.
Cash and cash equivalents fell ¥6,177m to ¥22,778m; operating, investing and financing cash flows were outflows of ¥616m, ¥1,795m and ¥3,765m.
Outlook and guidance
FY3/26 targets include orders of ¥95.5bn, net sales of ¥93.5bn, operating profit of ¥7.8bn and parent-attributable profit of ¥6,000m; EPS forecast is ¥272.51.
FY3/26 ordinary profit forecast is ¥8,400m; ROE is forecast at 8.4%, or 8.1% excluding estimated stock-sale profit of ¥390m.
Guidance was raised from the 8th Medium-term Management Plan; priorities include data-center and redevelopment/renovation demand and better project profitability.
Forecasts assume moderate economic recovery and strong construction investment; completion schedules, cost increases and global and market uncertainty may affect results.
Latest events from Hibiya Engineering
- H1 orders doubled on data-center demand, lifting backlog as FY guidance stayed unchanged.1982
Q2 2027 - Sales rose 29.6% and operating profit returned to the black; FY3/24 guidance held.1982
Q1 2024 - Orders surged 26.5%, while operating profit fell 33.2% in 9M FY3/2024.1982
Q3 2024 - Data-center-led orders surged 36.2%, while FY3/24 guidance remained unchanged.1982
Q2 2024 - Orders rose 20.8% on data-center demand, while project delays held back sales.1982
Q4 2024 - Sales and profit climbed on carryover work, while weak large-project orders cut bookings.1982
Q1 2025 - H1 profit surged on stronger project margins, while orders fell 39.8% YoY.1982
Q2 2025 - 9M profit surged despite lower orders; FY3/25 guidance remained unchanged.1982
Q3 2025 - Record orders and 43.1% operating-profit growth capped FY2026.1982
Q4 2026