Executive summary

  • Transitioned from exploration to execution-ready gold developer with a clear path to production at Gum Creek, supported by a robust DFS completed in July 2026.

  • DFS confirms a 2.4Mtpa operation targeting 880,000 ounces over 10 years, with strong economics and infrastructure in place.

  • Significant exploration success expanded the resource base to 2.3Moz, with ongoing drilling indicating further upside.

Financial highlights

  • Net loss after tax for FY2026 was $2.02 million, compared to a $0.97 million loss in FY2025.

  • Revenue was $513,000, mainly from interest income.

  • Cash and cash equivalents at year-end were $24.05 million, up from $0.5 million in FY2025.

  • Net assets increased to $72.14 million, driven by $39.7 million in capital raisings.

  • Market capitalisation rose to $204.5 million, with a closing share price of $1.05.

Outlook and guidance

  • Targeting Final Investment Decision (FID) in Q2 2027, with first gold production planned for H2 2028.

  • Early works, regulatory approvals, and team build-out scheduled for 2027, with EPC contractor mobilisation and plant commissioning by Q4 2028.

  • Project finance process underway, leveraging strong DFS metrics.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more