Integra Resources (ITR) Mining Forum Americas 2026 summary
Event summary combining transcript, slides, and related documents.
Mining Forum Americas 2026 summary
9 Oct, 2026Portfolio growth strategy
Production targeted to rise from 70,000–75,000 oz in 2026 to 200,000 oz when DeLamar comes online, then 250,000–300,000 oz with Nevada North.
Florida Canyon cash flow is intended to fund growth and permitting across DeLamar and Nevada North, reducing reliance on annual market financings.
Florida Canyon operations and outlook
The 2026 technical report extends mine life to 2033, adding eight years beyond the two years operated since acquisition; reserve growth came in part from drilling near existing operations.
Life-of-mine production is projected at 80,000–85,000 oz annually over the next eight years, versus 70,000–75,000 oz guided for 2026.
The next eight years are expected to generate an average $90 million of free cash flow; life-of-mine AISC is projected to decline to just over $2,300.
2026 costs reflect Central Pit pre-stripping, replacement equipment and heap-leach expansion brought forward from 2027; eight Caterpillar 785 trucks and two shovels support efficiency.
Production was 70,000 tons/day amid lower grades; higher grades from the Central Pit next year are expected to support the 80,000–85,000 oz range. 2026 guidance remains 70,000–75,000 oz.
Florida Canyon exploration
A 43,000 m drilling program is underway in 2026; saddle targets have returned grades 2–3x current mining grades, including 0.84 over 35 m and 0.83 over 29 m at Radio Tower.
Drilling through the north dump is testing the northern Madre Shear Zone extension; mining the dump is expected to provide access for resource conversion.
A 7,000 m Standard Mine program is planned for the balance of 2026 to assess a satellite deposit for trucking to Florida Canyon, 8 km away.
Latest events from Integra Resources
- Expanded production, robust pipeline, and permitting progress drive near-term growth.ITR
Corporate presentation - Advancing a high-growth, multi-asset gold platform with strong cash flow and resource scale.ITR
Corporate presentation - Record gold output and revenue drove higher cash flow, but costs and guidance increased.ITR
Q2 2026 - Mine life extended to 8 years, reserves up 74%, and $770M free cash flow targeted.ITR
Status update - Florida Canyon Mine delivers higher production, longer life, and strong cash flow for future growth.ITR
Corporate presentation - Florida Canyon cash flow drives DeLamar and Nevada North growth, with key 2026–2027 catalysts ahead.ITR
Corporate presentation - Record mining rates and strong margins in Q1 2026 support ongoing growth initiatives.ITR
Q1 2026 - Record gold output, strong earnings, and project milestones set up robust 2026 growth.ITR
Q4 2025 - Strong cash flow and growth pipeline support a leading resource base and long-term expansion.ITR
Corporate presentation