Executive summary

  • 9M26 operating revenues reached COP 12,412B and EBITDA COP 7,097B, both up 8% YoY; net profit was COP 1,792B, down 3% reported and up 5% excluding FX translation.

  • Cumulative capex rose 19% to COP 5.2T, supported by new projects, contract escalators, construction activity and IE Madeira consolidation.

  • 9M26 awards and transactions totaled USD 2,708M; investment commitments through 2030 were COP 28.1T, with 37 projects under development.

  • IE Madeira consolidation brought ownership to 100%; the transaction generated a COP 222B business-combination gain.

Financial highlights

  • 9M26 EBITDA margin was 57%, stable YoY; excluding construction, it was 78% vs. 74%. Net margin was 14% vs. 16%.

  • 3Q26 EBITDA was COP 2,208B, down 11% reported and stable excluding FX translation; net profit was COP 538B, down 23% reported and 9% lower excluding FX and the prior-year Paulista tariff-review appeal effect.

  • 9M26 EBIT was COP 6,023B, up 8%; net financial expenses rose to COP 2,123B from COP 1,737B.

  • Assets were COP 81.7T at September-end, up 7% vs. year-end 2025; liabilities rose 11%, while equity fell 4% to COP 17.2T.

  • Net income was down 1% excluding FX translation and special items.

Outlook and guidance

  • Growth plans span energy transmission, roads and telecommunications, with investment discipline and a long-term infrastructure focus.

  • Construction continued on 34 energy transmission projects, 9 renewals in Colombia and Chile, 172 Brazil grid projects and 3 road concessions; completed projects are expected to add 4,562 km of lines, 13,830 MVA and 296 km of roads.

  • The Caribbean pipeline includes more than USD 1.8B of projects, including Colectora 2 and key substation upgrades; Colectora 2 could transmit 3,000 MW of renewable energy, with technical definitions and tenders pending.

  • Colombia-Panama interconnection development is expected by end-2029; Kimal Lagunas is expected in 2027 and Kimal-Lo Aguirre in 2029.

  • Management expects the FX translation effect to be positive next year; investment decisions remain subject to returns exceeding the cost of capital and prudent debt management.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Interconexión Eléctrica