1 Sep, 2026Executive summary
Transitioned from bitcoin mining to a data center-first company focused on HPC/AI infrastructure, completing a direct listing in July 2026 and energizing the first data center at Ward County.
Controls 822 MW of power pipeline, with 323 MW contracted and $2.6B in contracted revenue, and maintains a debt-free balance sheet with strong liquidity.
Pivoted to stable, contracted cash flows, reducing exposure to bitcoin price volatility and positioning for significant AI-driven demand.
Completed a $400M capital raise and private placement, supporting expansion and liquidity.
Data center-first team with deep experience in digital infrastructure and capital discipline.
Financial highlights
Q2 2026 total revenue was $48.6M, up 31% year-over-year, with 90% from digital infrastructure leasing and $43.8M from that segment.
Adjusted EBITDA for Q2 2026 was $37.6M, representing a 77% margin.
Adjusted gross margin rose to 93% from 40% year-over-year; digital infrastructure segment achieved 99% margin.
Net loss for Q2 2026 was $35.3M, driven by a $28.2M non-cash Bitcoin loss and a $27.2M tax provision.
Ended Q2 with $415.7M in cash and 2,882 bitcoin valued at $168.7M; no outstanding borrowings.
Outlook and guidance
Reaffirmed 2026 outlook: total revenue of $190M–$195M, with 90–92% from digital infrastructure leasing.
Adjusted EBITDA expected at $137.5M–$142.5M; capital expenditures of $45M–$60M, mainly for Ward County and Midland expansion.
Cash rent expected to ramp from $23M in Q4 2026 to $183M annualized by end of 2028, with further increases as additional capacity energizes.
Latest events from Ionic Digital
- Secured $2.6B Nscale lease, 822 MW power pipeline, and Nvidia guarantee to drive AI growth.IOND
Investor Day 2026 - Direct listing highlights shift to AI/HPC infrastructure, $1.95B+ lease, and strong liquidity.IOND
Registration filing - Pivoting to digital infrastructure, the company leverages a $1.95B+ Nscale lease and $400M new capital.IOND