Ivanhoe Mines (IVN) Q2 2024 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2024 earnings summary
22 Apr, 2026Executive summary
Commissioned and ramped up the 5 Mtpa Phase III plant at Kamoa-Kakula, boosting annualized copper production capacity to over 600,000 tonnes; 100,812 tonnes produced in Q2 at a cash cost of $1.52/lb.
Completed Kamoa-Kakula Phase III and Kipushi concentrators ahead of schedule; both ramping to steady state, with Kipushi producing first zinc concentrate and ramp-up expected to steady state in September.
Kamoa-Kakula achieved record Q2 revenue of $817 million and EBITDA of $547 million, with a 67% margin, driven by higher copper prices and volumes.
First dividend of $98 million declared by Kamoa-Kakula, with 20% payable to the DRC government.
Platreef Phase I concentrator completed, with first ore feed deferred to H2 2025 to prioritize Shaft 3 and Phase II expansion.
Financial highlights
Payable copper tons sold increased 13% quarter-over-quarter; realized copper price was $4.34/lb in Q2 2024.
Ivanhoe recognized Q2 profit of $67 million and normalized profit of $115 million, both up from Q1; adjusted EBITDA reached a record $203 million.
Net cash position of $88 million at June-end after redeeming $575 million convertible notes; cash and cash equivalents stood at $246 million.
Drew $450 million in new term and working capital facilities; in-country facilities totaled $800 million at quarter-end.
C1 cash cost at Kamoa-Kakula was $1.52/lb, at the lower end of FY2024 guidance.
Outlook and guidance
Kamoa-Kakula maintains 2024 copper production guidance of 440,000–490,000 tonnes in concentrate; strong H2 expected with Phase III and power stability.
Kipushi 2024 zinc production guidance set at 100,000–140,000 tonnes in concentrate.
Platreef Phase I hot commissioning deferred to H2 2025 to prioritize Shaft 3 and Phase II expansion; targeting 4 Mtpa hoisting by 2026.
Project 95 aims to increase copper recoveries to ~95% and add up to 30,000 tonnes of copper production within 18 months; Phase IV and tailings retreatment under consideration.
Latest events from Ivanhoe Mines
- 2026–2027 copper output set at 290–420kt, targeting 500kt+ from 2028 at lower costs.IVN
Status update31 Mar 2026 - 2025 profit up to $228M; expansions and smelter ramp-up drive future growth.IVN
Q4 202519 Feb 2026 - Record copper output, strong financials, and major expansions despite operational challenges.IVN
Q3 202417 Jan 2026 - Record copper and zinc output, strong EBITDA, and major project milestones achieved in 2024.IVN
Q4 20248 Jan 2026 - Record Q1 profit, copper/zinc output, and project milestones drive strong growth.IVN
Q1 202523 Dec 2025 - Q2 2025 delivered strong copper output, resilient operations, and major project milestones.IVN
Q2 20251 Nov 2025 - Q3 profit was $31M as mine expansions advanced and cash reserves exceeded $1B.IVN
Q3 202531 Oct 2025 - World-class African mines drive growth, low costs, and leading ESG performance.IVN
Investor Presentation8 Jul 2025 - Record copper output, low costs, and major expansions drive industry-leading growth and returns.IVN
Investor Presentation8 Jul 2025