Investor presentation
Logotype for K92 Mining Inc

K92 Mining (KNT) Investor presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for K92 Mining Inc

Investor presentation summary

19 Apr, 2026

Growth strategy and production expansion

  • Targeting rapid growth to 500 koz AuEq per year, with Stage 3 expansion to 300 koz AuEq and Stage 4 to over 400 koz AuEq by late 2027.

  • Stage 3 process plant (1.2 mtpa) commissioned under budget, with first saleable production in October 2025 and commissioning completed December 2025.

  • 2026 production guidance of 190,000–225,000 oz AuEq at AISC of $1,250–$1,350/oz Au, with exploration budget of $31–35 million.

  • Major infrastructure upgrades include twin incline, ore pass system, ventilation, and pastefill system to boost underground productivity.

  • Fully funded for expansions, with strong cash balance ($231m), low debt ($50m), and significant available liquidity.

Resource growth and exploration

  • Large, high-grade resource base with 8.1 Moz AuEq M&I and 16.5 Moz AuEq inferred at Kora and Judd as of September 2023.

  • Blue Lake porphyry project hosts a 14.6 Moz AuEq inferred resource, open at depth and along strike.

  • Arakompa and Maniape vein systems show significant size and grade potential, with maiden resource at Arakompa targeted for H1 2026.

  • Exploration budget for 2026 is $31–35 million, with potential to increase to $40 million post-Stage 3 expansion.

  • Multiple high-priority near-mine and regional targets, including Wera, Karempe, and A1 porphyry, with drilling and geophysics identifying new zones.

Operational performance and cost profile

  • Among the highest-grade, lowest-cost gold mines globally, with reserve grades of 6.7 g/t AuEq and 2026 AISC guidance of $1,250–$1,350/oz Au.

  • Consistent operational performance with strong recoveries (gold: ~95%, copper: ~95%) and record quarterly production in Q1 2026 (46,743 oz AuEq).

  • Major sustaining capex since 2023 is directed toward upcoming expansions.

  • Underground mine productivity transformed by infrastructure upgrades, including the completion of the internal ramp and ore pass system.

  • Three mining fronts now producing ore, increasing to four in 2027 with pastefill online.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.