Keel Infrastructure (KEEL) Q3 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 earnings summary
6 Nov, 2026Executive summary
Continued pivot from Bitcoin mining to North American HPC/AI infrastructure; U.S. mining ended in June, while legacy mining continues in Canada. No HPC capacity was generating revenue at quarter-end.
Moses Lake construction began in September after permits cleared; the 18 MW modular facility is expected to be the first energized site generating HPC revenue in 2027.
Lease discussions advanced across three near-term sites with creditworthy prospects, but the prior year-end target for three leases is no longer expected amid permitting delays.
Financial highlights
Q3 revenue was $27.6M vs. $68.0M YoY; operating loss narrowed to $7.7M from $18.5M, while gross loss widened to $14.6M from $2.3M.
Continuing-operations loss was $62.4M, or $0.10 per share, vs. $11.0M; net loss was $62.7M vs. $38.8M.
Adjusted EBITDA was a loss of $27.4M vs. income of $19.2M; G&A expense rose to $34.3M from $17.2M.
Sold 2,520 Bitcoin for $192.2M; holdings were nominal at September 30, with future Québec production to be sold daily.
Outlook and guidance
No further lease-date guidance; the prior goal of three leases by year-end is no longer expected, with updates focused on site-development progress.
Moses Lake is expected to energize in 2027; Sharon and Panther Creek substations are expected to energize in 2027, with revenue anticipated from early 2028 and capacity ramping through 2028.
Panther Creek and Scrubgrass load-study updates are expected in Q1 2027; studies assess potential added capacity of up to 500 MW and 1.3 GW, respectively.
Unrestricted cash liquidity was $780M as of November 4; management said it covers pre-lease capex and cash SG&A through 2028, with no external financing expected before lease signing.
Latest events from Keel Infrastructure
- Power-ready sites, permitting progress and liquidity anchor leasing and growth plans.KEEL
KBW Virtual AI Summit - Revenue down 50% to $30.4M as focus shifts to HPC, with $819M liquidity for expansion.KEEL
Q2 2026 - Strategic transition to AI/HPC data centers leverages unique power assets and site readiness.KEEL
Fireside chat - Board expansion, new director election, and rights plan ratification all approved.KEEL
EGM 2024 - Strategic US pivot with major HPC campus development and first revenues targeted for 2027.KEEL
21st Annual Needham Technology, Media, & Consumer Conference - Q1 2026 revenue dropped 23% as net loss widened and $533M liquidity supports HPC/AI growth.KEEL
Q1 2026 - Revenue up 72% to $229M as the business pivoted to HPC/AI, but losses widened amid transition.KEEL
Q4 2025 - Q3 revenue up 156% to $69M, net loss $46M, pivoting to U.S. HPC/AI with $1B+ liquidity.KEEL
Q3 2025 - Q2 revenue rose 17% YoY to $42M; 2024 growth fully funded, U.S. and HPC/AI expansion underway.KEEL
Q2 2024