24 Mar, 2026Strategic focus and regional context
Concentrates on gold and copper development in the Arabian-Nubian Shield, leveraging geological similarities to Western Australia for growth potential.
Operates in Ethiopia and Saudi Arabia, with a pipeline of projects and joint ventures, including GMCO with ARTAR and Hancock Prospecting.
Ethiopia and Saudi Arabia have prioritized mining sector reforms, licensing, and foreign investment, with Ethiopia targeting a GDP mining share increase from 1.94% to 14% over ten years.
Saudi Arabia's Vision 2030 and Ethiopia's economic reforms have accelerated sector growth and attracted global players.
Flagship projects and resource base
Tulu Kapi Gold Mine in Ethiopia is advancing toward production, with a 1.05Moz reserve at 2.12g/t and a 1.72Moz resource at 2.65g/t.
Projected open pit production is 135Koz gold per year, with underground expansion planned to lift output to 179Koz per year.
Hawiah (Saudi Arabia) is a top-three base metals discovery, with 36.2Mt at 0.82% copper, 0.86% zinc, 0.64g/t gold, and 10g/t silver; targeted for production in 2027.
Jibal Qutman (Saudi Arabia) holds a 0.9Moz gold resource, with feasibility studies underway and recent discoveries expanding potential.
Financial structure and economics
Tulu Kapi project finance totals $320M, with $240M secured debt and $80M equity risk capital, involving African development banks and local investors.
Project NPV (100%) is $1,069M at $3,000/oz gold, with an IRR of 89%; at $2,400/oz, NPV is $690M and IRR 65%.
Average annual net cash flow projected at $213M at $3,000/oz gold, with AISC of $918/oz at $2,400/oz.
Financing syndicate includes banks, government, contractors, and regional investors, with KEFI expected to retain 80-85% beneficial interest in Tulu Kapi.
Latest events from KEFI Gold And Copper
- Final contract signings and $320M financing are imminent, with major works and expansion set for 2025.KEFI
Investor update24 Mar 2026 - Tulu Kapi financing nears completion with strong local support and key milestones set for September.KEFI
Investor update24 Mar 2026 - Major resource upgrades and positive regional trends drive project growth and financing momentum.KEFI
Investor update24 Mar 2026 - Funding secured, three-mine diversification, and main market ambitions drive rapid growth.KEFI
Investor update24 Mar 2026 - Tulu Kapi targets mid-2026 gold production as project financing and resource expansion advance.KEFI
H2 202324 Mar 2026 - Tulu Kapi project nears full financing and launch; group loss narrows on JV dilution gain.KEFI
H2 202424 Mar 2026 - Tulu Kapi advances toward production as Saudi projects expand, reinforcing regional leadership.KEFI
AGM 2024 presentation24 Mar 2026 - Tulu Kapi advances as Ethiopia's flagship mining project amid sector reforms and strong growth.KEFI
Investor presentation24 Mar 2026 - Tulu Kapi project accelerates toward gold production as financing and Saudi expansion progress.KEFI
AGM 2025 presentation24 Mar 2026