Status update summary

15 Oct, 2026

Production and shipments

  • HMC production was 334.1kt (+12% YoY); excavated ore rose 22%, partly offset by 12% lower grades, primarily at WCP A near the end of its Namalope mine path.

  • Ilmenite output was 233.6kt (+12% YoY, +59% QoQ); primary zircon reached 13.0kt (+6%), rutile 2.2kt (+22%) and concentrates 44.5kt (+109%).

  • 2026 ilmenite guidance reduced from ~800kt to 710–750kt due to WCP A commissioning; shipments expected at ~1.05Mt versus prior guidance above 1.1Mt.

  • Q3 shipments were 242.9kt (+7% YoY); delayed vessels and product-loading protocols constrained loading time. Cash operating costs expected toward the upper end of the $215–225m guidance range.

WCP A upgrade and operational projects

  • WCP A averaged 3,100tph capacity and 49% utilisation in Q3, versus ~2,760tph and 42% in H1; consistent nameplate capacity of 3,500tph is expected in H1 2027.

  • Interim winch-brake software improved resilience; a permanent first-dredge solution is expected by year-end, with pump-system, mining-rate and throughput improvements continuing.

  • Downstream debottlenecking, reliability and tailings measures were implemented; further improvement is expected in Q4.

  • SMO 2 equipment is on site, with commissioning expected in Q4 2026; estimated cost is $10.9m, of which $7.6m was incurred. SMO 3 is planned for H1 2027 at $2.1m.

Markets and growth opportunities

  • Ilmenite markets remained soft amid oversupply and elevated titanium feedstock availability in China; Q3 average received price rose QoQ on product mix, but a weaker Q4 price is expected on soft markets and lower-value mix.

  • Zircon prices strengthened in Q3 as reduced production and tighter availability outside China constrained supply; further improvement is expected in Q4.

  • PFS identified potential to produce up to 4kt of monazite concentrate annually at low capital outlay, alongside additional ilmenite, zircon and rutile production; DFS and offtake discussions are commencing.

  • DFS is expected to take up to one year; first production is expected about two years after a decision to proceed.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Kenmare Resources