KGL Resources (KGL) H2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2026 earnings summary
30 Sep, 2026Executive summary
FY2026 marked a transformational year, with the Jervois Copper-Silver-Gold Project becoming fully funded to production through a US$300m PMPA with Wheaton and a post-year-end A$300m equity raise, totaling A$689m in funding with no project debt.
The Baseline Economic Model (BEM) confirmed strong project economics: post-tax NPV of A$839m (8% discount), post-tax IRR of 31%, and C1 cost of US$1.65/lb copper, with significant leverage to copper price increases.
Project execution focus shifted to construction readiness, with first copper concentrate targeted for H1 CY2028 and full processing capacity in H2 CY2028.
Leadership and governance were strengthened with key board and executive appointments.
Financial highlights
Net loss for FY2026 was A$3.84m, compared to A$3.02m in FY2025.
Cash and cash equivalents increased to A$25.3m at 30 June 2026 from A$5.1m the prior year, reflecting funding inflows.
Total assets rose to A$162.6m (from A$131.7m), with exploration and evaluation assets at A$134.6m.
Equity increased to A$136.8m (from A$130.2m), driven by new share issues.
EBITDA and EBIT remained negative, reflecting pre-production status.
Outlook and guidance
Fully funded to production, with A$70m liquidity buffer and A$20m allocated for exploration.
FID and principal construction targeted for H2 CY2026; first copper concentrate in H1 CY2028.
Exploration program aims to extend mine life and resource base beyond current 10-year plan.
Latest events from KGL Resources
- Fully funded Jervois project advances to construction with strong economics and copper market tailwinds.KGL
Q4 2026 TU - A$300m equity raising secures funding for a 10-year, high-grade copper project with strong economics.KGL
Investor presentation - Shovel-ready copper project targets 30ktpa output, strong economics, and major exploration upside.KGL
Corporate presentation - Loss of $2.67M, $8.08M raised post-year-end, Jervois Project targets 2027 production.KGL
H2 2024 - Advanced project development, raised $11M, and targets construction in 2026 amid rising copper demand.KGL
H1 2026 - A$11 million raised, project advanced, and record metal prices boost project economics.KGL
Q2 2026 TU - Jervois Project advanced with higher resources, robust feasibility, and ongoing funding needs.KGL
H2 2025 - AGM highlighted robust funding, expanded resources, and strong copper market outlook.KGL
AGM 2025 - Jervois Project advances with resource growth, feasibility updates, and 2027 production target.KGL
AGM 2024