King Wan Corporation (554) H1 2023 earnings summary
Event summary combining transcript, slides, and related documents.
H1 2023 earnings summary
2 Nov, 2026Executive summary
1H2023 revenue rose to S$41.2m from S$35.6m as construction activity increased, but the period ended in a S$5.1m net loss versus S$0.4m profit in 1H2022.
Higher material and manpower costs on pre-pandemic projects drove gross margin from 10.1% profit to a 0.4% gross loss; total comprehensive loss was S$7.1m, including a S$2.2m FVTOCI investment loss.
Financial highlights
Revenue increased S$5.5m to S$41.2m; gross loss was S$0.2m versus gross profit of S$3.6m in 1H2022.
Operating expenses included S$5.3m of administrative expenses, up S$2.8m, and S$60k of other operating expenses; finance costs rose 28% to S$471k.
Net loss was S$5.067m versus net profit of S$435k; income tax credit was S$280k versus expense of S$149k.
Basic and diluted EPS was a loss of 0.73 cents versus earnings of 0.12 cents in 1H2022.
Outlook and guidance
Approximately S$166.8m of M&E engineering contracts were on hand; M&E remains the core business, with M&E and portable lavatory rentals expected to continue generating income.
Management expects M&E engineering to remain challenging over the next 12 months due to labour shortages, rising material costs and challenging economic conditions; liquidity will be monitored.
Latest events from King Wan Corporation
- Revenue grew, but cost inflation drove a S$4.8m loss and squeezed margins to 0.5%.554
H2 2023 - H1 returned to profit, while construction and liquidity risks persisted.554
H1 2024 - S$12.4m profit rebound, driven largely by associate fair value gains, amid operating and credit risks.554
H2 2024 - Revenue and margins improved, but profit fell as one-off prior-period gains faded.554
H1 2025 - Improved M&E margins and a stronger order book offset only part of the sharp decline in associate profits.554
H2 2025 - Revenue halved amid project delays; associate profits and a S$198.3m M&E order book provide support.554
H1 2026 - Project timing drove a sharp loss, while a S$242.5m order book supports recovery visibility.554