Kootenay Silver (KTN) Corporate presentation summary
Event summary combining transcript, slides, and related documents.
Corporate presentation summary
31 Aug, 2026Project overview
La Cigarra is located within the historic Parral Silver District, an area with over 350 years of silver production and significant historical output exceeding 500 million ounces of silver from nearby districts.
The project is situated 20 km north of the Francisco del Oro-Santa Barbara camp, with a well-established mining infrastructure in the region.
Economic highlights
After-tax NPV at consensus metal prices is $763 million (5% discount rate), with an IRR of 41%; at spot prices, NPV is $1,295 million and IRR is 64%.
Initial capital cost is $332 million, sustaining capital is $80 million, and payback period is 1.9 years after tax.
Average annual after-tax revenue is $107 million, with an average all-in sustaining cost of $18.73/oz Ag.
Production and mine life
Average annual silver production over the first five years is 6.22 million ounces; life-of-mine (LOM) average is 4.55 million ounces per year.
Total LOM payable silver production is 63.6 million ounces over a 14-year mine life.
Processing rate is 6,000 tonnes per day, with an average silver recovery of 89.3%.
Latest events from Kootenay Silver
- La Cigarra’s PEA and two-project drilling target development and resource growth.KTN
Precious Metals & Critical Minerals Virtual Investor Conference - La Cigarra’s US$763M PEA NPV and Columba’s 60,000m drill program anchor growth.KTN
Corporate presentation - Large silver resources, robust project economics, and aggressive exploration drive strong growth potential.KTN
Corporate presentation - Aggressive drilling at Columba targets major resource expansion in Mexico's silver-rich districts.KTN
Investor presentation