5 Oct, 2025Executive summary
Achieved significant operational progress at the Kachi Project, including resource upgrades, cost reductions, and infrastructure milestones.
Completed sale of non-core assets, enhancing liquidity and extending financial runway.
Advanced environmental permitting and power supply solutions, positioning Kachi for final investment decision.
Implemented substantial cost reductions, including workforce rationalisation and executive changes.
Financial highlights
Loss after tax for FY2025 was $21.1 million, a significant improvement from the prior year's $54.0 million loss.
Cash and cash equivalents at 30 June 2025 were $12.4 million, with pro-forma cash of $28.0 million after subsequent capital raises.
Achieved $13.6 million in proceeds from the sale of non-core assets.
Total assets at year-end were $163.0 million; net assets were $144.4 million.
No dividends declared or paid.
Outlook and guidance
Focused on securing EIA approval, optimising power solutions, and progressing strategic review for Kachi.
Market conditions for lithium expected to improve, with analysts forecasting price recovery and supply deficits.
Near-term objectives include maintaining financial flexibility and advancing toward a final investment decision.
Latest events from Lake Resources
- Kachi project advances toward production with robust resources, new technology, and strong market tailwinds.LKE
Investor presentation16 Mar 2026 - Kachi Project progresses with improved economics and liquidity, despite a wider net loss.LKE
H1 20261 Mar 2026 - Kachi lithium project advances with robust resources, updated economics, and strategic positioning.LKE
Precious Metals & Critical Minerals Virtual Investor Conference10 Feb 2026 - Lithium demand and prices surge as a key Argentine project advances with tech and cost gains.LKE
Noosa Mining Investor Conference17 Nov 2025 - CapEx down 16%, lithium grades up, and robust economics drive project competitiveness.LKE
Investor Update16 Nov 2025 - Capital raise boosts liquidity and Kachi project economics, with costs and risks managed.LKE
Q1 2026 TU23 Oct 2025 - Kachi resource upgraded to 8.2 Mt LCE, cash outflows cut 40%, and strategic review in progress.LKE
Q4 2025 TU22 Jul 2025 - Net loss narrowed, liquidity improved, and Kachi Project milestones advanced amid market headwinds.LKE
H1 202516 Jun 2025 - Kachi DFS confirms strong economics, but Lake faces losses and delays amid lithium market headwinds.LKE