Lake Resources (LKE) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
13 Oct, 2026Kachi project
Catamarca, Argentina project targeting 25 ktpa battery-grade lithium carbonate in Phase 1; potential Phase 2 could add another 25 ktpa, with a 25-year mine life. Kachi is 80% owned by Lake Resources and 20% by Lilac Solutions.
Total resource of 11.1 Mt LCE, including 8.2 Mt measured and indicated and 2.9 Mt inferred; DFS design basis is 249 mg/L, with average ore reserve concentration of 268 mg/L.
Exploitation EIA approval was granted in September 2026; FEED is advancing. A 200 m lagoon exclusion zone is not expected to materially affect the ore reserve estimate or wellfield plan for the 25 ktpa profile.
Project economics and technology
Phase One DFS Addendum: US$1.16B capex, US$5,895/t opex, US$1.5B pre-tax NPV10 and 22.5% pre-tax IRR; NPV assumes a US$20.5/kg average lithium carbonate price.
Lilac Gen 4 ion-exchange technology targets ~90% recovery; DLE modules cut 50%, DLE capex 39% and DLE opex 40% versus the original DFS.
Addendum design reduced well count ~22% and plant footprint 15–20% versus the original DFS; further cost reductions may come from higher brine concentration and Lilac Gen 5 technology.
Milestones and priorities
Completed a demonstration plant that processed 5.2 million litres of brine and produced more than 1,300 kg of lithium carbonate at >99.5% purity; Phase One DFS and its August 2025 addendum were completed.
Completed power-supply FEED in 2025; the 2026 public consultation was held in August and DIA approval followed at the end of September.
Near-term priorities include submitting the RIGI application, advancing FEED, optimizing technical and commercial power solutions, finalizing offtake and strategic partnerships, securing project capital and achieving FID.
Target schedule is first lithium 33 months after FID and full capacity 42 months after FID.
Latest events from Lake Resources
- Kachi advanced toward development, but financing and final environmental approval remain pivotal.LKE
H2 2026 - Progressed Kachi EIA, secured $10.6M liquidity, and expanded strategic partnerships amid market volatility.LKE
Q3 2026 TU - Kachi project milestones achieved, cost cuts implemented, and net loss widened to $54M.LKE
H2 2024 - Kachi project advances toward production with robust resources, new technology, and strong market tailwinds.LKE
Investor presentation - Kachi Project progresses with improved economics and liquidity, despite a wider net loss.LKE
H1 2026 - Kachi lithium project advances with robust resources, updated economics, and strategic positioning.LKE
Precious Metals & Critical Minerals Virtual Investor Conference - Lithium demand and prices surge as a key Argentine project advances with tech and cost gains.LKE
Noosa Mining Investor Conference - CapEx down 16%, lithium grades up, and robust economics drive project competitiveness.LKE
Investor Update - Kachi Project advances, cash outflows drop, and liquidity rises amid lithium price headwinds.LKE
Q3 2025 TU