Latin Resources (LRS) Q2 2024 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2024 TU earnings summary
13 Jun, 2025Executive summary
Transitioned from explorer to developer in Q2 2024, with drilling completed and a major resource upgrade at Salinas Lithium Project; DFS completion due Q3 2024 and FID targeted for Q4 2024, construction expected to start Q1 2025.
Colina Lithium Deposit MRE upgraded to 70.9Mt at 1.25% Li₂O; global Salinas MRE now 77.7Mt at 1.24% Li₂O, among the largest undeveloped lithium resources.
Cash burn reduced significantly, with A$21M cash at 30 June 2024 and full funding to FID in Q4 2024.
Advanced offtake and funding discussions underway, targeting low-cost capital structure for project development.
Non-core asset divestment and ESG initiatives progressing, including a planned spin-out of ESG Minerals Ltd.
Financial highlights
Cash at bank of A$21M (US$14M) and $1.3M in investments as of 30 June 2024.
Net cash outflow for the quarter was $18.2M, mainly due to exploration and evaluation expenditure.
Exploration and evaluation expenditure for the quarter totaled $13.4M.
Cash burn significantly reduced after completion of Mineral Resource Estimate (MRE).
Estimated 1.1 quarters of funding available at current burn rate, but cash burn expected to decrease post-exploration.
Outlook and guidance
Fully funded to FID in Q4 2024, with construction targeted to commence in Q1 2025 pending approvals; surplus cash forecast at 31 December 2024.
DFS to confirm Salinas as a large, low-capex, low-opex project; permits expected to allow construction in Q1 2025.
DFS release expected Q3 2024, with first production targeted for 2026.
Funding strategy and offtake decision to be released ahead of FID.
Planalto maiden MRE expected Q3 2024, targeting a global resource >100Mt.
Latest events from Latin Resources
- All-share deal adds a major Brazilian lithium asset, boosting diversification and global scale.LRS
M&A Announcement2 Feb 2026 - Pilbara Minerals to acquire Latin Resources, securing a top-tier lithium asset in Brazil.LRS
Q3 2024 TU13 Jun 2025 - Pilbara Minerals to acquire Latin Resources after strong Salinas resource growth and narrowed loss.LRS
H1 202413 Jun 2025 - Salinas Lithium Project targets low-cost, ESG-compliant lithium production by 2026 in Brazil.LRS
Investor Presentation13 Jun 2025