Latrobe Magnesium (LMG) H2 2024 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2024 earnings summary
31 Mar, 2026Executive summary
Significant progress on the Latrobe Magnesium Project, including completion and commissioning of the hydromet section and production of MgO in May 2024.
Capital costs for the demonstration plant increased to $60.7M, with an additional $5.2M estimated for completion.
Raised $23.3M in capital during the year, plus $6M in July 2024 via an underwritten rights issue.
Advanced plans for a 10,000tpa commercial plant and a 100,000tpa plant in Malaysia, securing land and progressing permits.
Financial highlights
Net loss after tax of $4,742,588 for FY2024, compared to a $2,438,497 loss in FY2023.
Revenue of $262,823 and other income of $6,321,565, mainly from R&D tax rebates.
Total assets increased to $95.4M from $62.5M year-over-year.
Cash and cash equivalents at year-end were $565,150, down from $6.9M.
Equity raised through multiple placements and a share purchase plan, totaling $23.3M.
Outlook and guidance
MgO plant scheduled for official handover and ramp-up to 1,000tpa production in October 2024.
Stage 2 commercial plant feasibility and funding underway, with operations targeted for June 2026.
Stage 3 Malaysian plant progressing with land secured and permits pending.
2024 R&D tax rebate expected to be $13.3M net, with 2025 rebate estimated between $11M and $13M.
Latest events from Latrobe Magnesium
- Loss increased as plant commissioning advanced; funding and government support secured.LMG
H1 202622 Mar 2026 - Demonstration Plant achieved MgO production; major financing and expansion plans underway.LMG
Q1 2026 TU28 Oct 2025 - Low-emission magnesium production advances with A$8m equity raise and commercial scale-up plans.LMG
Investor Presentation13 Oct 2025 - Net loss narrowed to $2.66M as plant commissioning and capital raisings advanced project milestones.LMG
H2 202530 Sep 2025 - Project milestones advance as cash reserves stand at $1.95M, with 2.22 quarters of funding.LMG
Q1 2025 TU10 Sep 2025 - Demonstration Plant launch, capital raise, and funding needs define the quarter.LMG
Q4 2025 TU30 Jul 2025 - Demonstration Plant launch, new funding, and Sarawak project advances mark a pivotal quarter.LMG
Q3 2025 TU22 Jun 2025 - Demonstration plant nears continuous MgO production as funding and expansion accelerate.LMG
Q4 2024 TU13 Jun 2025