29 Oct, 2026Executive summary
Advanced Orion CMC negotiations for a strategic Kabanga equity investment; commercial terms were substantially concluded, with legal work ongoing and closing targeted as soon as possible.
Kabanga engineering, procurement, permitting, infrastructure and workforce preparation advanced toward a Q1 2027 FID target.
PGM recycling testing demonstrated >99% platinum and palladium recovery; project FID is also targeted for Q1 2027.
Musongati work included historical-data review, KoBold Metals digitization engagement and evaluation of a proposed laterite drilling program.
Financial highlights
For the nine months ended September 30, 2026, revenue was $1.9m versus $0.5m year over year, driven by Simulus technical and laboratory services.
Net loss attributable to shareholders was $13.5m; basic and diluted loss per share were each $0.15.
Operating cash use was $7.9m, investing cash use was $24.1m and financing activities provided $34.1m during the nine-month period.
General and administrative expenses were $16.3m versus $12.5m, primarily reflecting $4.9m in non-cash share-based payment charges.
Outlook and guidance
Kabanga FID is targeted for Q1 2027, subject to the Tanzania Framework Agreement amendment, Joint Financial Model, lender due diligence and financing terms.
PGM recycling feasibility study completion and FID are targeted for Q1 2027; optimization testing and commercial plant design continue through Q1 2027.
The Kabanga 220 kV overhead-line ESIA uplift is on track for Q4 2026 completion, with related EPC tenders scheduled for release in Q4 2026.
The $18.3m undrawn bridge-loan amount was available until November 29, 2026, subject to the Framework Agreement amendment.
Latest events from Lifezone Metals
- Kabanga targets Q1 2027 FID after a feasibility study showing $1.58B after-tax NPV.LZM
Investor presentation - Registration allows resale of 500,000 shares tied to nickel project warrants; no proceeds from share sales.LZM
Registration filing - Kabanga FID shifts to Q1 2027 as projects advance and liquidity reaches ~$56M.LZM
H1 2026 - Kabanga is a world-class, low-cost nickel project advancing with strong economics and strategic backing.LZM
Corporate presentation - Kabanga is set to become a leading, low-cost nickel producer with robust economics and global impact.LZM
Investor presentation - All AGM resolutions passed, including director re-elections and auditor ratification.LZM
AGM 2026 - Nickel price surge, $68M liquidity, and project milestones drive improved outlook.LZM
Q1 2026 - Kabanga Nickel Project achieves 100% ownership, robust funding, and execution readiness for FID.LZM
H2 2025 - Up to $250M in securities offered, with debenture conversions and a focus on clean energy metals.LZM