Lindian Resources (LIN) AGM 2026 presentation summary
Event summary combining transcript, slides, and related documents.
AGM 2026 presentation summary
22 Nov, 2026Execution and catalysts
Stage 1 FID approved in Aug 2025; active mining began Jul 2026, with 149,000t of ore stockpiled and grid power energised in early Oct 2026.
First Kangankunde concentrate production and first SARECO processing targeted for Dec 2026; first Nacala shipment targeted for Jan 2027 at an indicative ~850dmt per month thereafter.
Stage 1 commissioning targeted for late Nov 2026; Stage 2 DFS and oxide separation DFS completion targeted for Dec 2026, with timing subject to change.
Stage 1 is fully allocated; 45,000dmtpa of Stage 2 volumes allocated, while Stage 2 remains conceptual and subject to DFS and FID.
Integrated mine-to-oxide strategy
Kangankunde mine and concentrator in Malawi feed the SARECO cracking and leaching plant in Kazakhstan, with downstream oxide separation planned alongside global sales.
SARECO is 100% owned and operational, with 11,800tpa production capacity and exclusive marketing rights over its MREC output; first processing is targeted for Dec 2026.
An 8,000tpa oxide separation facility is in DFS with Carester and Tetra Tech; its stated capacity is potential processing capacity, not a production target.
The Stage 1 plant capacity objective is 20,000tpa; the DFS-supported average production remains 15,323tpa, and 20,000tpa is not a revised production target.
Kangankunde economics and resource
Mineral Resource totals 261Mt at 2.14% TREO, including 1,132kt contained NdPr; Ore Reserve totals 23.7Mt at 2.9% TREO.
Stage 1 upfront capex is US$40m; post-tax NPV8 is A$831m, post-tax IRR is 80%, and post-tax payback is ~18 months.
Stage 1 TREO operating cost is US$2.92/kg FOB; the feasibility study describes this as lowest-cost-quartile.
The deposit has a 0.2:1 waste-to-ore strip ratio; simple crushing, milling, gravity and magnetic separation produces a premium 55% TREO concentrate.
Latest events from Lindian Resources
- Mining is underway, while SARECO ownership and downstream partnerships advance integration.LIN
Q1 2027 TU - Kangankunde advanced to mining, SARECO acquired, $108M cash, and first production set for Q4 2026.LIN
H2 2026 - Strategic partnership and low CapEx drive rapid, high-margin growth and rare earth market expansion.LIN
Investor update - Construction advances at Kangankunde, targeting Q4 production and strong market positioning.LIN
Diggers & Dealers Mining Forum 2026 - Kangankunde construction accelerates, 100% ownership secured, and cash at A$56.97 million.LIN
Q2 2026 TU - Kangankunde construction and mining milestones achieved; fully funded for Q4 2026 first production.LIN
Q4 2026 TU - Full-scale construction and a strategic acquisition position the company for integrated rare earths production in 2026.LIN
Q3 2026 TU - Kangankunde Rare Earths Project advanced with robust economics, $35M raised, and net loss reduced.LIN
H2 2024 - Kangankunde project fully funded and under construction, with net loss of $8.79M and strong cash reserves.LIN
H1 2026