Lithium Americas (LAC) Q1 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2025 earnings summary
19 Mar, 2026Executive summary
As of March 31, 2025, cash and restricted cash totaled $446.9 million, with working capital of $405.9 million.
Major construction at Thacker Pass is underway, with earthworks nearly complete and the first permanent concrete placed in May 2025.
Thacker Pass Phase 1 is fully funded following a $250 million investment from Orion Resource Partners and additional contributions from GM and Lithium Americas to the JV.
Final investment decision for Phase 1 construction was announced, with $191.6 million and $100 million contributed by the company and GM, respectively.
$78.2 million in construction and project-related costs were capitalized in Q1 2025.
Financial highlights
Net loss for Q1 2025 was $11.5 million, compared to $6.3 million in Q1 2024, mainly due to higher G&A and transaction costs.
Net loss per share was $0.05, versus $0.04 in the prior year quarter.
Cash and restricted cash decreased by $147.3 million from December 31, 2024.
Mineral properties, plant, and equipment increased by $76.9 million to $475.8 million.
Total assets were $1,018.5 million, with total liabilities of $83.5 million at quarter end.
Outlook and guidance
First draw on the $2.26 billion DOE Loan is expected in Q3 2025.
Completion of Phase 1 of Thacker Pass is targeted for late 2027, with ramp-up in 2028 and engineering expected to exceed 90% by year-end 2025.
Detailed engineering is over 60% complete as of March 31, 2025.
First occupancy of the Workforce Hub for construction workers is targeted for the second half of 2025.
The company expects sufficient cash resources for at least the next 12 months.
Latest events from Lithium Americas
- $2.26B DOE loan, $625M GM JV, and $250M Orion investment drive Thacker Pass progress.LAC
Q3 202419 Mar 2026 - Thacker Pass fully funded for 2H24 construction start; cash up, net loss in H1 2024.LAC
Q2 202419 Mar 2026 - Construction advances with strong financing and cash, targeting late 2027 completion.LAC
Q2 202519 Mar 2026 - Thacker Pass construction accelerates with major funding and higher net loss in Q3 2025.LAC
Q3 202519 Mar 2026 - Strong progress at Thacker Pass with robust financing and construction on track for 2027 completion.LAC
Q4 202519 Mar 2026 - Thacker Pass is set to become the largest, lowest-cost U.S. lithium producer by 2028.LAC
Corporate presentation19 Mar 2026 - Thacker Pass, the largest U.S. lithium project, is fully funded and on track for 2027 completion.LAC
Gabelli Funds' 16th Annual Specialty Chemicals Symposium2 Dec 2025 - Thacker Pass advances as the largest U.S. lithium project, fully funded and under major construction.LAC
Corporate Presentation14 Sep 2025 - Thacker Pass targets 40,000 t/y lithium carbonate by 2027, with full funding and major permits secured.LAC
June 2025 Thacker Pass Site Tour Presentation14 Sep 2025