5 May, 2026Executive summary
Operational ramp-up at Kayelekera Uranium Mine continues, with safety prioritized and new leadership and infrastructure upgrades enhancing performance.
No Lost Time Injuries recorded, reflecting a strong safety culture.
Product acceptance achieved at Orano conversion facility in France, providing delivery flexibility.
Mining now active across three fronts, with high-grade stockpiles exceeding 200,000 tons at quarter end.
Sulphuric acid supply restored, but reagent management and maintenance impacted processing performance.
Financial highlights
Cash operating costs for the quarter were AUD 36 million, impacted by critical spares, insurance, duties, and elevated freight costs; not reflective of steady-state costs.
Outflows for the next quarter are forecast at AUD 38 million, with a significant portion allocated to capital projects, especially the power grid connection.
AUD 85 million in unrestricted cash at quarter end, providing flexibility for ramp-up and working capital.
Net cash used in operating activities for the quarter was A$37.7M, mainly for production costs.
Placement raised A$76M and SPP raised A$3M before costs.
Outlook and guidance
Expectation of more stable operations and consistent ramp-up in coming months, with recovery improvements anticipated as work streams are executed.
First uranium shipment targeted for this quarter, pending permitting and logistics through Namibia.
Letlhakane updated Mineral Resource Estimate and preliminary feasibility study expected in H2 CY26 and H1 CY27, respectively.
Inventory financing facility to be announced soon, structured as a debt facility secured by uranium inventory, more attractive than equity or hybrids.
May and June expected to deliver improved throughput and production, trending toward steady-state in Q2 CY26.
Latest events from Lotus Resources
- Uranium output surged, but acid supply disruptions paused production; major funding secured.LOT
Q4 2026 TU - Operational reset and funding secure Kayelekera's path to steady uranium production and growth.LOT
Investor presentation - First uranium production achieved at Kayelekera, with strong financing and future cash flow outlook.LOT
H2 2025 - Net assets surged to $127.4M after Letlhakane acquisition and $30M capital raise, despite a $24.5M loss.LOT
H2 2024 - First yellowcake produced at Kayelekera, ramp-up funded by strong capital raises and financing.LOT
H1 2026 - Kayelekera achieved first uranium production in 2025, targeting 2.4Mlbpa steady-state in 2026.LOT
Investor presentation - A$76M equity raise supports Kayelekera ramp-up and Letlhakane development amid strong uranium demand.LOT
Investor presentation - Kayelekera ramps up uranium output as Letlhakane advances, leveraging strong market demand.LOT
2025 Precious Metals Summit - Zurich - First yellowcake produced at Kayelekera; ramp-up, contracts, and cost controls on track.LOT
Investor Update