Lundin Mining (LUN) CMD 2026 summary
Event summary combining transcript, slides, and related documents.
CMD 2026 summary
8 Jul, 2026Strategic transformation and growth focus
Shifted to a copper-focused growth strategy, acquiring major South American assets and forming a 50:50 Vicuña JV with BHP, aiming for top-ten global copper producer status and targeting over 500,000 tons/year copper production over the next decade.
Portfolio transformed through acquisitions (Josemaria, Caserones, Filo Corp) and divestitures, increasing copper's share of revenue from 63% in 2022 to 85% in 2025, with revenue rising from $3B to $4.1B and EBITDA margins improving from 40% to 46%.
Achieved 19% growth in copper production per share and 330% growth in gold mineral resources per share from 2022 to 2026.
Operational discipline and safety performance improved, with industry-leading safety metrics, zero fatalities, and record low TRIF of 0.15 in Q1 2026.
Sustainability initiatives include 100% renewable power sourcing, first CSRD-compliant report, emissions reduction, and community engagement.
Operational excellence and efficiency
Full Potential program implemented across all sites, delivering cost reductions (e.g., Chapada: $11.8 to $10.6/tonne, Caserones: $20 to $17.9/tonne, Candelaria: $19.9 to $19.03/tonne) and up to 11% mine site cost reduction.
Chapada achieved 11% cost reduction, improved fuel efficiency, and reduced strip ratio by 29%; Candelaria and Caserones saw similar operational gains.
Saúva project at Chapada sanctioned, adding 15,000 tons copper and 45,000 oz gold annually from 2029, with CapEx reduced to $110M.
Caserones cathode plant utilization increased from 55% to 80%, targeting 30,000–40,000 tons cathode in 2026, with further debottlenecking planned.
Candelaria’s underground expansion and insourcing expected to boost free cash flow by $56M–$90M/year and enhance productivity and mine life.
Vicuña District and major growth projects
Vicuña District, a 50:50 JV with BHP, is a supergiant copper-gold-silver system, targeting peak annual output of 500,000 tons copper, 800,000 oz gold, and 20M oz silver, with a 25-year average of 400,000 tons copper and 700,000 oz gold.
Multi-stage development: Josemaria (stage 1), Filo del Sol oxides (stage 2), and Filo sulfides (stage 3), with Stage 1 capex at $7.1B and Stages 2 & 3 adding $11.1B.
RIGI application approved, granting 40 years of stability and export benefits; project sanction decision expected by year-end.
Los Helados acquisition (31%) adds high-grade resource and synergy potential with Caserones; scoping study underway.
Exploration ongoing across district, with significant upside from underexplored targets and further resource growth potential.
Latest events from Lundin Mining
- Vicuña District drives transformative copper growth, robust cash flow, and industry-leading sustainability.LUN
Corporate presentation13 Jul 2026 - Record Q2 revenue and EBITDA, copper growth, and reduced capex guidance support outlook.LUN
Q2 20249 Jul 2026 - Vicuña is a top global copper-gold-silver resource with high-grade zones and major growth potential.LUN
Investor Update9 Jul 2026 - Strong Q1 results, asset sale, and Vicuña JV drive growth and strengthen the balance sheet.LUN
Q1 20259 Jul 2026 - Record Q3 2025 results with higher copper guidance, lower costs, and strong cash flow.LUN
Q3 20258 Jul 2026 - Q1 2026 delivered strong financials, copper output, and major growth project progress.LUN
Q1 202613 May 2026 - All management proposals passed; shareholder emissions proposal was rejected.LUN
AGM 20267 May 2026 - Record revenue, strong copper growth, and major project investments drive strong outlook.LUN
Q4 202511 Apr 2026 - Staged 70+ year project targets top-tier copper output, low costs, and major resource growth.LUN
Status update18 Feb 2026