Magnora (MGN) Q3 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 earnings summary
30 Oct, 2026Executive summary
Diversified portfolio totaled 10,195 MW net at 30 Sep 2026; data-center capacity reached 910 MW gross, up from 650 MW in Q2.
Cash was NOK 742.1m with a NOK 150m undrawn credit line; Q3 opex was NOK 11.3m net of intra-group charges.
Strategy focuses on de-risking projects before sale, growing data centers and selectively developing renewable-data center hybrids.
Financial highlights
Q3 net loss was NOK 28.4m versus NOK 34.9m in Q2; operating loss was NOK 33.1m and net financial items were positive NOK 4.7m.
Revenue was NOK 1.3m; total expenses were NOK 34.3m, including NOK 23.4m of data-center platform opex and development costs and NOK 3.6m of share-incentive costs.
Net operating cash flow was negative NOK 25.8m; investing cash flow was negative NOK 36.6m, including M&A and an Oslo AI/EDGE data-center site acquisition.
Q3 EBITDA was negative NOK 32.4m; development and M&A expenses rose to NOK 18.1m from NOK 13.2m year over year.
Outlook and guidance
The 2026 portfolio target is 12 GW net; approximately 2,500 MW of renewable projects are in sales processes or ready to enter them.
Target is one to two renewable project or cluster sales annually through 2033; projects are generally marketed after firm grid-connection dates are secured.
Sales and earnouts are expected in coming months; South African earnouts could exceed NOK 100m, excluding Helios and Evolar, subject to milestones.
Opex net of intra-group charges is expected to remain at the Q3 level; two UK projects totaling 156 MW expect updated grid offers from October 2026 to March 2027 and connection availability in 2028, subject to offer terms.
Latest events from Magnora
- Diversified 10,015 MW portfolio and NOK 1 billion shareholder returns drive rapid growth.MGN
Pareto Securities' 33rd Annual Energy Conference presentation - Data center IPO raised NOK 650m, portfolio exceeds 10 GW, and strong liquidity supports growth.MGN
Q2 2026 - Nordic-focused data center developer targets high returns with a 585 MW portfolio and rapid growth.MGN
Investor presentation - 10 GW portfolio reached; data center and renewables drive growth despite Q1 net loss.MGN
Q1 2026 - 60% portfolio growth to 10.4 GW, strong cash, and focus on data centers and renewables.MGN
Q4 2025 - 16x Helios return, NOK 1B+ capital returned, 12.5 GW portfolio, zero debt, strong cash.MGN
Q3 2024 - Q2 net profit surged to NOK 374.2m, fueled by Helios sale and Hermana demerger gains.MGN