Mahvie Minerals (MAHVIE) Q4 2024 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2024 earnings summary
5 Jun, 2025Executive summary
No revenue generated in Q4 or full year 2024; focus remains on exploration and project development.
Net loss after tax improved to -928 TSEK in Q4 2024 from -1,663 TSEK year-over-year; full-year net loss after tax was -4,969 TSEK, an improvement from -6,828 TSEK.
Key activities included initial ore modeling at Haveri and a directed share issue raising approximately 1.9 MSEK.
Post-period, an EGM approved the share issue and drilling permits were secured for the Haveri gold project.
Financial highlights
Q4 2024 net loss after tax: -928 TSEK (Q4 2023: -1,663 TSEK); EPS: -0.02 SEK (Q4 2023: -0.04 SEK).
Full-year 2024 net loss after tax: -4,969 TSEK (2023: -6,828 TSEK); EPS: -0.12 SEK (2023: -0.29 SEK).
Equity at year-end: 32,214 TSEK (2023: 35,783 TSEK); cash and cash equivalents: 1,676 TSEK (2023: 5,645 TSEK).
Cash flow from operations in Q4: -641 TSEK (Q4 2023: -3,074 TSEK); total Q4 cash flow: 529 TSEK (Q4 2023: 2,831 TSEK).
Solidarity ratio at year-end: 81.5% (2023: 82.9%).
Outlook and guidance
Short-term focus on advancing the Haveri gold project in Finland; Mofjell base metal project in Norway to follow.
Market conditions for gold, copper, and zinc remain favorable, supporting project development.
Latest events from Mahvie Minerals
- Strong project milestones and capital raises position for continued gold exploration growth.MAHVIE
Q1 202620 May 2026 - Åkerberg acquisition, Haveri studies, and 14.6 MSEK share issue mark a pivotal year.MAHVIE
Q4 202517 Feb 2026 - Q3 2025 saw no revenue, a net loss, strong cash inflow, and strategic gold project expansion.MAHVIE
Q3 202511 Nov 2025 - Q2 net loss narrowed, gold focus sharpened, and 15 MSEK rights issue over-subscribed.MAHVIE
Q2 202519 Aug 2025 - No revenue, narrowed loss, and positive ore modeling mark Mahvie Minerals' Q3 2024.MAHVIE
Q3 202413 Jun 2025 - No revenue, robust equity, and Mofjell ranks among top global zinc projects.MAHVIE
Q2 202413 Jun 2025 - Q1 net loss narrowed as Mahvie Minerals advanced Haveri drilling and secured new funding.MAHVIE