Mapletree Logistics Trust (M44U) AGM 2024 presentation summary
Event summary combining transcript, slides, and related documents.
AGM 2024 presentation summary
28 Oct, 2026Portfolio and operating performance
Diversified portfolio of 187 properties across 10 markets; AUM S$13.2b, GFA 8.2m sqm, occupancy 96.0% and WALE 3.0 years at 31 Mar 2024.
Developed markets represented ~70% of portfolio AUM and revenue; total portfolio revenue was S$733.9m in FY23/24.
Occupancy was 97.5% excluding China and 93.2% in China; rental reversions were +7.7% excluding China, -7.9% in China and +1.4% portfolio-wide.
No tenant represented more than 4% of gross revenue; 915 tenants, top 10 tenants ~22% of revenue and weighted average lease expiry 3.0 years.
Financial and capital position
FY23/24 gross revenue rose 0.4% YoY to S$733.9m; net property income was broadly stable at S$634.9m versus S$634.8m.
Distributable income increased 3.3% YoY to S$447.1m, while DPU fell 0.1% to 1.38 cents on an enlarged unit base; S$41.6m of divestment gains cushioned higher borrowing costs and weaker currencies.
AUM increased 3.2% YoY to S$13.2b; NAV per unit declined 4.2% to S$9.003, largely reflecting a S$470.9m currency translation loss.
84% of debt was hedged or fixed-rate; ~78% of the next 12 months' distributable amount was hedged into or derived in SGD. Each 25 bps base-rate increase could reduce quarterly distributable income by ~S$0.5m.
Aggregate leverage was 36.8%; debt totaled S$5.31b, average debt duration was 3.8 years and S$950m of committed facilities was available to refinance S$275m due in FY24/25.
Portfolio rejuvenation
Executed over S$1.1b of acquisitions for 12 modern Grade A assets in FY23/24, deepening connectivity across developed and emerging markets.
Four acquisitions in Delhi, Kuala Lumpur, Ho Chi Minh City and Hanoi had agreed property values totaling S$241.0m and completion dates from February to June 2024.
The 51 Benoi Road redevelopment is under construction; estimated cost S$205m, GFA to rise 2.3 times to 887,000 sqft and completion expected in 1H 2025.
Proposed Subang redevelopment has estimated costs of MYR536m (~S$173m), potential GFA of 1.4m sqft and expected completion in 1H 2028, subject to land-amalgamation approvals.
Over S$200m of divestments were announced or completed in FY23/24 at an average premium to valuation of almost 13%, freeing capital for modern assets with higher growth potential.
Latest events from Mapletree Logistics Trust
- Stable DPU, 96.4% occupancy and active capital recycling support portfolio resilience.M44U
Investor presentation - Operating growth edged DPU higher as portfolio renewal advanced despite reported-profit pressures.M44U
Q2 26/27 - Distributions grew as portfolio resilience and sustainability investments advanced.M44U
AGM 2023 presentation - Portfolio renewal and hedging support growth amid currency and funding headwinds.M44U
AGM 2025 presentation - 96.9% occupancy anchors a portfolio shifting capital into modern logistics assets.M44U
AGM 2026 presentation - DPU edged higher as acquisitions expanded the portfolio, despite currency and financing headwinds.M44U
Q1 23/24 - Stable operating results, higher distributable income, and persistent currency and China headwinds.M44U
Q4 23/24 - DPU rose 0.9% as acquisitions and divestment gains offset FX and China headwinds.M44U
Q2 23/24 - Adjusted DPU rose in 4Q as occupancy improved to 96.9%, despite FX and divestment headwinds.M44U