Executive summary

  • Q3 revenue fell 35% YoY to $164.2M; net income was $632.1M and Adjusted EBITDA was $857.7M, both boosted by substantial digital-asset fair-value gains.

  • Strategy is shifting toward contracted AI/HPC and critical IT infrastructure, with Bitcoin mining retained as a flexible workload while higher-value uses of power are developed.

  • Energized capacity totaled 1.9 GW across 19 data centers, with a potential path to ~4.8 GW subject to Long Ridge closing and Matagorda energization.

Financial highlights

  • Q3 revenue was $164.2M versus $252.4M YoY; lower average Bitcoin prices drove most of the decline in mining revenue.

  • Net income was $632.1M versus $123.1M; diluted EPS was $1.28 versus $0.27, including an $885.3M non-cash digital-asset and receivable fair-value gain.

  • Adjusted EBITDA was $857.7M versus $395.6M YoY; the non-GAAP measure included fair-value gains.

  • Cash and cash equivalents were $946.5M; cash and Bitcoin holdings totaled $3.78B, including 34,012 BTC at quarter-end.

  • G&A was $75.8M versus $85.3M YoY, down 11%, as lower stock-based compensation partly offset Exaion and expanded-footprint costs.

Outlook and guidance

  • Two lease signings remained targeted before year-end, though tenant diligence and closing items could push timing into 2027.

  • Long Ridge closing was expected in the coming weeks, subject to customary conditions; total potential power capacity could reach ~4.8 GW after closing and full Matagorda energization.

  • Matagorda plans call for construction to begin in late 2026, up to 1 GW by October 2027 and up to 2 GW by April 2028, subject to approvals and milestones.

  • Exaion’s pipeline exceeded $3B in total contract value, with ~$1B targeted for delivery by end-2027; pipeline demand is not contracted or committed.

  • Third-party hosting contracts representing ~29% of energy capacity are scheduled to expire from Q3 2027 through Q1 2028, reducing hosting costs over time.

Partial view of Summaries dataset, powered by Quartr API