  • Two diamond drill rigs operated throughout the quarter, accelerating infill drilling and resource definition work.

  • Strong assay results confirmed high-grade silver-lead and copper-gold mineralisation, including significant shallow intercepts in the Starter Zone and nearby areas.

  • Strategic A$22 million investment by Kinterra Capital secured a 19.99% equity stake, boosting pro-forma cash to A$36.6 million.

  • Boxcut design optimisation reduced excavation volume by ~100,000 BCM, lowering upfront capital requirements.

  • Pre-Feasibility Study (PFS) workstreams advanced, targeting higher-throughput mining scenarios and updated Mineral Resource Estimate in H2 2027.

Financial highlights

  • Exploration and evaluation expenditure for the quarter was A$2.66 million.

  • Mining production and development activities cost A$406,000 for the quarter.

  • Cash and cash equivalents at quarter end were A$33.4 million, up from A$14.6 million in the previous quarter.

  • Net cash from financing activities was A$21.1 million, primarily from the Kinterra Capital placement.

  • Estimated quarters of funding available is 14.71, indicating strong liquidity.

Outlook and guidance

  • Focus remains on expanding the Indicated Resource base and advancing the PFS toward completion in H2 2027.

  • Updated Mineral Resource Estimate expected in the second half of 2027.

  • Proceeds from the Kinterra investment will fund drilling, Mining Licence application, and PFS advancement.