MC Mining (MCM) Q2 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2026 TU earnings summary
10 Jun, 2026Executive summary
Makhado Project construction advanced, with hot commissioning of the coal plant set for March 2026 and key milestones achieved despite weather delays.
Uitkomst Colliery faced operational challenges, with ROM coal production down 40% year-over-year and sales of high-grade coal down 34%.
Health and safety improved, with only one LTI group-wide and Makhado achieving 1,005 days LTI-free.
Vele Colliery remains suspended, but geological and mine planning assessments were completed.
Financial highlights
Available cash and facilities at period end were $2.9 million, down from $13.2 million in the previous quarter.
Net cash used in operating activities was $2.6 million for the quarter.
Net cash used in investing activities was $14.0 million, mainly for property, plant, and equipment.
Net cash from financing activities was $6.2 million, including $7 million from share subscription.
Production cost per saleable tonne at Uitkomst rose 32% year-over-year to $116/t.
Outlook and guidance
Makhado Project hot commissioning of the coal plant is expected by March 2026, with operational readiness activities ongoing.
Various options are under review to address Uitkomst's production underperformance, with external consultants engaged.
Environmental and water use licensing for Greater Soutpansberg Projects to commence in H1 CY2026.
Latest events from MC Mining
- Zero LTIs, Makhado commissioning progress, Uitkomst suspended, cash at US$2.9M, coal prices up.MCM
Q4 2026 TU - Losses widened sharply on lower revenue and major cost increases, with funding uncertainty persisting.MCM
H2 2024 - Production fell and costs rose at Uitkomst, but cash reserves strengthened via new funding.MCM
Q1 2025 TU - Uitkomst production fell 26% and costs rose 70% as cash reserves dropped to $4 million.MCM
Q2 2025 TU - Makhado progressed on schedule as Uitkomst output and revenue declined, but liquidity improved.MCM
Q3 2025 TU - Losses widened on sharply lower revenue and output, but new equity and loan extension support liquidity.MCM
H1 2025 - Makhado Project advances on schedule as Uitkomst Colliery boosts efficiency amid lower coal prices.MCM
Q4 2025 TU - Losses widened on impairments and lower sales, but KDG funding and cost cuts improved liquidity.MCM
H2 2025 - Makhado Project nears commissioning as safety improves and cash reserves rise to $13.1 million.MCM
Q1 2026 TU