Medallion Metals (MM8) Q1 2027 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2027 TU earnings summary
28 Oct, 2026Executive summary
Final regulatory approvals secured for Ravensthorpe; development began at Kundip and construction advanced at Forrestania’s Cosmic Boy Concentrator (CBC).
A $60m placement lifted available liquidity to approximately $175m, supporting project development, ramp-up and resource drilling.
Early Production Strategy (EPS) preparations progressed, with third-party ore deliveries underway and gold processing targeted to start in the December 2026 quarter.
Financial highlights
Cash at 30 September 2026 was $97.0m; cash and cash equivalents were reported as $96.981m.
Quarterly net cash used in operating activities was $10.899m; investing activities used $3.320m and financing activities provided $57.183m.
Receipts from customers were $834k and interest received was $683k in the quarter.
Outlook and guidance
Gold processing under the EPS was a focus for the December 2026 quarter; processing of Kundip ore remains targeted for Q2 CY2027.
CBC steady-state production is forecast for H2 2027; the modified plant is designed for 650ktpa of Ravensthorpe sulphide ore at P80 75 microns.
December-quarter priorities include Kundip portal and decline development, CBC construction, and drilling and MRE updates at Lounge Lizard and Teddy Bear.
Latest events from Medallion Metals
- Strong cash position and project execution drive growth, despite higher net loss from development costs.MM8
H2 2026 - First gold and copper production is imminent, with robust resources and rapid growth ahead.MM8
Diggers & Dealers Mining Forum 2026 - Strong cash position, new high-grade lode discovery, and early gold production strategy advance growth.MM8
Q4 2026 TU - Regulatory-approved drilling and strong cash position support growth at a robust gold-copper project.MM8
Q4 2024 TU - Completed PFS, boosted Ore Reserves, reduced losses, and secured funding for RGP growth.MM8
H2 2024 - Secured exclusivity for key plant acquisition, raised $5M, and advanced RGP development.MM8
Q1 2025 TU - Strong RGP study, high-grade drilling, and Forrestania deal progress drive growth outlook.MM8
Q2 2025 TU - Net loss increased, but asset base and cash grew amid capital raising and strategic project moves.MM8
H1 2025 - Transformational year with FNO acquisition, strong project metrics, and improved financial position.MM8
H2 2025