Metis Energy Limited (L02) H2 2024 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2024 earnings summary
9 Nov, 2026Executive summary
FY2024 revenue increased to S$4.79m from S$3.68m, while net loss widened to S$13.26m from S$10.19m; the prior-year loss included discontinued operations.
Development advanced in Vietnam and Australia: operational rooftop solar capacity reached 47.15MWp, and the 111MWp DC/94MW AC Queensland utility project entered construction.
Financial highlights
Continuing-operations revenue rose to S$4.79m from S$3.68m, supported by a full-year contribution from 12.4MWp of projects delivered in FY2023 and 4.6MWp delivered in Vietnam in FY2024.
Loss from continuing operations was S$13.26m versus S$9.55m; loss before tax was S$13.19m versus S$9.50m.
Other income fell to S$1.99m from S$6.40m; FY2024 included a S$1.07m fair-value gain on the electricity derivative, while FY2023 included a S$4.35m gain on disposal of an associate.
Finance costs increased to S$4.97m from S$2.25m, including S$3.01m interest on related-party amounts versus S$0.38m.
Cash and bank deposits were S$16.62m versus S$36.47m; operating cash outflow was S$3.90m, investing outflow S$107.28m and financing inflow S$91.35m.
Outlook and guidance
Target completion of the 111MWp DC/94MW AC Queensland solar project by 2H2025; expected generation is up to 250GWh annually.
Growth plan targets an additional 630MWp of solar and wind and 200MWh of battery storage over five years; gross installed renewable capacity target is 800MWp by 2030.
FY2025 priorities include strengthening risk and compliance practices and continuing assessment of physical climate-risk impacts on key assets.
Latest events from Metis Energy Limited
- Revenue grew, but the absence of prior-year land-sale gains drove a steep profit decline.L02
H1 2023 - Revenue held near S$4.7m as Vietnam solar grew and Queensland entered commissioning.L02
H2 2025 - A S$10.189m FY2023 loss accompanies a pivot to solar growth in Vietnam and Australia.L02
H2 2023 - Revenue rose 53%, but higher project costs, financing and FX losses drove a S$4.9m net loss.L02
H1 2024 - Project impairments and derivative losses widened H1 losses as renewable construction spending accelerated.L02
H1 2025 - Project Gunsynd lifted revenue, while FX gains helped narrow the H1 loss.L02
H1 2026