Metro Mining (MMI) Q3 2026 TU earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Metro Mining Limited

Q3 2026 TU earnings summary

29 Oct, 2026

Executive summary

  • Q3 shipments reached 2.114M WMT, up 17% QoQ, and site EBITDA improved to A$7.0/WMT from A$4.4/WMT; both remained below plan amid operational constraints and higher costs.

  • Management said constraints had been addressed, with October’s second half exceeding 30,000 tonnes per day; Q4 priorities are production recovery, lower unit costs and cash generation.

Financial highlights

  • Q3 mined volume was 2.013M WMT versus 1.919M WMT in Q2 and 2.197M WMT in Q3 2025; shipments were 2.114M WMT versus 1.799M and 2.246M WMT, respectively.

  • CIF pricing was A$60.8/WMT, up from A$57.1/WMT in Q2 and below A$64.5/WMT in Q3 2025; FOB margin was A$43.4/WMT versus A$43.9/WMT and A$48.6/WMT.

  • Operating cash flow was A$10.552M; quarter-end cash was A$16.834M, down from A$23.765M at quarter start.

  • Bauxite pricing rose 9% in US$/DMT terms and 6.5% in A$/WMT from Q2 to Q3; exchange-rate movements offset part of the USD gain.

Outlook and guidance

  • FY 2026 shipment guidance was reset to 6.0–6.5M WMT; management expects a strong final quarter and may load in January if safe operating windows are available.

  • Q4 customer pricing was agreed at US$2–4/DMT above Q3 levels; contracted freight positions are expected to keep costs below market rates.

  • Two binding offtake contracts with existing customers cover 4.5M WMT per year for 2027–2029; no specific 2027 production guidance was given.

  • The operation is considered capable of 7–8 Mt annual output, with demand at or above that range; wet-season plans include potential January shipping opportunities.