MMG (1208) Q1 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2026 earnings summary
5 Oct, 2026Executive summary
Copper production rose 9% year-over-year to 128,698 tonnes, driven by Las Bambas and Kinsevere; all operations remained on track to meet full-year production guidance.
Zinc production declined 3% year-over-year to 50,263 tonnes, while gold rose 24% and silver 27%, supporting lower C1 costs across operations.
Q1 production was in line with expectations; safety improved quarter-over-quarter, with management focused on stable operations, cost optimization and community engagement.
Financial highlights
Las Bambas C1 cost was $0.45/lb versus FY guidance of $1.20–$1.40/lb, primarily due to higher by-product credits.
Khoemacau C1 cost was $1.25/lb versus $2.00–$2.30/lb guidance; silver credits contributed about $1/lb. Dugald River was $0.77/lb versus $0.80–$0.95/lb guidance.
Kinsevere C1 cost was $2.69/lb, within FY guidance of $2.50–$2.90/lb; Rosebery reported -$1.80/lb versus guidance of -$0.60 to -$0.10/lb.
Higher precious-metal prices and operational efficiency lowered C1 costs; guidance may be reassessed if favorable prices persist.
Outlook and guidance
Las Bambas 2026 copper guidance is 380,000–400,000 tonnes, with a 400,000-tonne target and planned ore mix of 56% Ferrobamba and 44% Chalcobamba.
2026 production guidance: Kinsevere 65,000–75,000 tonnes of copper, Khoemacau 48,000–53,000 tonnes of copper, Dugald River 170,000–180,000 tonnes of zinc and Rosebery 45,000–55,000 tonnes of zinc.
Khoemacau expects Q2 concentrate output to increase as new mining equipment arrives and availability improves; Las Bambas copper sales are expected to move closer to production from Q2 as port inventories are drawn down.
Khoemacau Phase 2 targets first concentrate in H1 2028, lifting annual copper capacity from ~50,000 to 130,000 tonnes; life-of-mine average C1 cost is expected below $1.60/lb.
Khoemacau Phase 3 pre-feasibility is underway; approval to advance to feasibility is targeted for H1 2027, with feasibility approval expected in 2028.
Latest events from MMG
- COVID-19 and Las Bambas disruptions drove lower H1 earnings and a $158m attributable loss.1208
H1 2020 - Record revenue and profit, reduced net debt, and major growth investments marked H1 2026.1208
H1 2026 - Stable copper and zinc output, lower cost guidance and ~$1.6 billion raised for growth.1208
Q2 2026 - Record copper and zinc output, strong by-product credits, and Khoemacau expansion set up 2026.1208
Q4 2025 - Copper output rose 54% YoY, with Las Bambas dividends supporting Khoemacau’s loan repayment.1208
Q2 2025 - Record revenue and profit growth in 2025, with robust operations and major expansion projects.1208
H2 2025 - Copper output jumped 76% year-over-year, offsetting zinc declines and supporting a strong outlook.1208
Q1 2025 - MMG acquires Anglo American's Brazilian nickel assets for up to US$500M, boosting global presence.1208
M&A Announcement - Net profit up 200% to $366M, EBITDA up 40%, with major growth and balance sheet strengthening.1208