Modern Mining Technology (MDRN) Registration filing summary
Event summary combining transcript, slides, and related documents.
Registration filing summary
23 Nov, 2026Company overview and business model
Early-stage e-waste processor uses proprietary pre-concentration and aqueous purification to recover gold, silver, copper, palladium and other metals; plastics are sold to downstream recyclers.
Process chain: secure e-waste from primary recyclers, separate plastics and metals into metallic sand concentrate, then purify metals for sale into industrial supply chains.
Greenville, North Carolina site is a pilot plant at ~10% of planned commercial capacity; commercial PCP is designed for 8,000 tonnes/year, while the APP is sized for concentrate from up to four PCPs.
Pilot tests produced MSC and a doré bar; June 2023 update cited ~1,100 lb MSC produced and assay results from a 650 lb sample of 5 oz gold, 14 oz silver and 450 lb copper.
Financial performance and metrics
FY2022 revenue was nil and net loss was $2.78M, versus nil revenue and a $2.09M net loss in FY2021; comprehensive loss was $2.64M in FY2022 vs $2.08M in FY2021.
Cash was $713,896 and total liabilities were $4.53M at Dec. 31, 2022; total equity was a $3.22M deficit and working capital deficit was $194,332.
FY2022 operating cash use was $2.41M, investing cash use $200,643 and financing cash inflow $2.89M; FY2021 operating cash use was $622,768.
Audited IFRS statements carry a material going-concern uncertainty; recurring losses, working-capital deficiency and dependence on additional financing cast substantial doubt on continued operations.
Use of proceeds and capital allocation
Estimated net proceeds are $8.565M at $5.00/share, or ~$9.945M with full over-allotment, after estimated $635,000 offering expenses.
Allocation: 39% capital expenditures, 43% working capital/general corporate purposes, 14% marketing and 4% R&D; management retains discretion within these priorities.
Target milestones include $5.5M for commercial PCP/APP build-out by IPO +6 months, commissioning and capacity ramp by IPO +12 months, and steady-state commercial production targeted by IPO +18 months.
Proceeds are expected to fund operations for the next 24 months; management cautions that changing circumstances may accelerate cash use.
Latest events from Modern Mining Technology
- A pilot-stage e-waste metals recovery model seeks IPO funding to scale commercial production.MDRN
Registration filing - IPO proceeds target commercial e-waste processing, with scale-up and funding risks still substantial.MDRN
Registration filing - A pre-revenue e-waste processor seeks IPO funding to turn pilot results into commercial production.MDRN
Registration filing - An e-waste metals venture seeks $8.6M to move from pilot testing toward commercial production.MDRN
Registration filing - E-waste recovery is pitched as a faster, lower-capex route to gold and critical metals.MDRN
Corporate presentation - Amendment adds a filing fee table without changing the prospectus.MDRN
Registration filing