Montage Gold (MAU ) Q4 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2025 earnings summary
29 May, 2026Executive summary
Construction at the Koné project is ahead of schedule and on budget, with first gold pour targeted for late Q4-2026 via the oxide circuit and hard-rock circuit completion expected in Q2-2027.
Over 9.0 million construction hours have been worked, with a workforce exceeding 3,000 and a strong focus on local employment (>90%).
Key infrastructure milestones include completion of CIL tanks, ball mill shell installation, water storage, and permanent camp, with the airstrip and resettlement village fully operational.
Exploration remains robust, with 114,699 meters drilled in 2025 and a $16 million, 99,000-meter drill program underway for 2026.
Acquisition of African Gold Limited is expected to close in Q2-2026, adding the Didievi project to the portfolio.
Financial highlights
Total capital committed for Koné project construction reached $572.8 million as of March 2026, about 65% of the $885 million total upfront capital expenditure.
Cash and cash equivalents at year-end 2025 were $191.8 million, with total liquidity and project funding sources of $559.4 million.
Cash flows used in investing activities increased to $113.9 million in Q4-2025, reflecting ongoing construction.
Cash flows from financing activities rose slightly to $157.3 million in Q4-2025.
Outlook and guidance
First gold pour is targeted for late Q4-2026 through the oxide circuit, with hard-rock circuit completion in Q2-2027.
Updated life of mine plan and new resource estimates for Koné and Gbongogo Main deposits are expected in 2026.
Ongoing exploration and integration of new discoveries aim to enhance the production profile from the onset.
Latest events from Montage Gold
- Koné project construction is ahead of schedule, targeting first gold in late 2026 with strong economics.MAU
Corporate presentation4 Jun 2026 - Koné Project construction and resource expansion drive asset growth, with first gold pour set for Q2-2027.MAU
Q4 202429 May 2026 - Koné project construction is ahead of schedule, with strong liquidity and major exploration progress.MAU
Q1 202614 May 2026 - Koné project construction is ahead of schedule, targeting first gold in late Q4-2026.MAU
Corporate presentation14 May 2026 - Koné Gold Project targets first gold in late 2026, with strong growth, funding, and ESG focus.MAU
Corporate presentation13 Apr 2026 - Koné project construction is on track for late 2026 gold production, fully funded and expanding.MAU
Corporate presentation23 Mar 2026 - Construction and exploration milestones achieved; robust funding supports Q2-2027 gold pour target.MAU
Q3 202526 Nov 2025 - Koné project construction and exploration advance ahead of schedule, with strong liquidity and outlook.MAU
Q2 202512 Sep 2025 - Major gold project in Côte d'Ivoire advances rapidly, targeting early production and strong growth.MAU
2025 Precious Metals Summit - Beaver Creek12 Sep 2025