NANO Nuclear Energy (NNE) TD Nuclear Roundtable (Virtual) summary
Event summary combining transcript, slides, and related documents.
TD Nuclear Roundtable (Virtual) summary
8 Oct, 2026KRONOS construction preparation and schedule
Advancing EPCM and construction-partner discussions, final schedule development, hiring, and vendor due diligence; definitive contracts targeted in the coming one to two quarters.
EPCM award potentially in Q4; construction management/general contractor RFP completion and potential award targeted for Q1.
TRISO fuel and enriched uranium contracts targeted in Q4, as is graphite procurement; reactor pressure vessel contract targeted for Q1-Q2.
Targeting construction in H2 2027, beginning as soon as the construction permit is approved; a one- to two-month lag is possible.
NRC safety evaluation is expected in September 2027, with approval thereafter; management sees potential for the review timeline to compress.
Licensing, commissioning and project costs
Operating license application ideally targeted for late 2027 to early 2028; approval targeted in 2029, followed by fueling and commissioning in 2029 or 2030.
Current gross CapEx estimate is $300 million-$350 million; an updated Class Five estimate, with much of it at Class Four standards, is targeted around year-end or January, potentially for the February earnings call.
Exploring 30%-40% investment tax credits, including a potential IRS private letter ruling; eligibility work reflects the University of Illinois ownership and operation model and research-reactor classification.
Updated cost work will support a State of Illinois funding request; DOE university fuel services and University of Illinois funding are also under discussion to reduce project costs.
Customer pipeline and Tillman framework
Tillman Global Holdings announced a nonbinding commercial framework for a $100 million investment; definitive warrant and restricted-stock agreements are being developed.
Most of the proposed investment is tied to firm purchase orders, with a minority tied to development milestones; potential milestones include site development, NRC licensing, site characterization and drilling.
Targets associated with the Tillman opportunity include 2 GW of nuclear capacity by the mid-2030s and potentially 6 GW by 2040.
Joint development agreements and formal NRC licensing for projects could advance in the coming one to two years, ahead of the University of Illinois project coming online in 2029 or 2030.
Latest events from NANO Nuclear Energy
- KRONOS MMR advances in NRC licensing, with $580M liquidity and STS acquisition fueling growth.NNE
Q3 2026 - Shareholders will vote virtually on director elections, auditor ratification, and governance and energy issues.NNE
Proxy filing - Advancing modular microreactors for data centers, targeting commercial operation by 2029–2030.NNE
TD Cowen’s 10th Annual Nuclear Fuel Cycle and Next Generation Nuclear Roundtable - Advancing modular microreactors and fuel logistics with global partnerships and regulatory progress.NNE
Investor presentation - KRONOS MMR reached NRC permit stage, with $569M liquidity and expanding partnerships.NNE
Q2 2026 - Developing advanced nuclear microreactors and fuel solutions, targeting commercialization in the 2030s.NNE
Registration Filing - Cash surged to $577.5M, fueling KRONOS MMR progress, partnerships, and global expansion.NNE
Q1 2026 - Advanced KRONOS MMR, raised $600M+, and expanded pipeline with strong cash growth.NNE
Q4 2025 - Drilling begins for KRONOS MMR, advancing modular nuclear energy and industry partnerships.NNE
Collaboration