Company overview and business model

  • Vertically integrated developer and operator of digital infrastructure and integrated power assets; pivoted in H2 2025 from legacy natural gas operations to data center campuses.

  • Strategy centers on assembling and entitling Powered Land, then developing Powered Shells and build-to-suit assets in power-advantaged markets, initially the Permian Basin.

  • Flagship Texas Critical Data Centers project spans 493 acres in Ector County, is designed for over 1 GW of potential compute capacity, and targets initial power delivery as early as end-2027.

  • Planned execution combines power, land and connectivity with engineering, construction, procurement, generation and sustainability partners for AI hyperscalers.

Financial performance and metrics

  • TCDC drew the full $20 million Term Loan A-1 in April 2026; an additional $60 million was drawn under Term Loans A-2 and A-3 in October 2026.

  • A $116 million letter of credit for Luminant ET Services was backed by cash collateral of at least 102% of the undrawn amount, approximately $118.3 million at issuance; funding included $60 million of loan proceeds and approximately $58.3 million cash.

Use of proceeds and capital allocation

  • No proceeds from resales go to the issuer, except cash received if Macquarie Warrants are exercised; resale proceeds otherwise go to selling stockholders.

  • Selling stockholders bear commissions, discounts, brokerage fees, taxes and marketing costs; registration expenses are the issuer’s responsibility.

Partial view of Summaries dataset, powered by Quartr API