Signed 30-year Administrative Mining Contracts for Carangas Project, pending Bolivian legislative approval.
Filed updated Carangas Project PEA, showing robust economics and increased throughput, including gold zone.
Entered cooperation agreement with Carangas community to support project development.
Appointed new CEO and CFO, confirming leadership transition.
Financial highlights
Net loss for the year ended June 30, 2026 was $4.19 million ($0.02/share), compared to $3.76 million ($0.02/share) last year.
Net loss for the quarter was $0.99 million ($0.01/share), compared to $0.89 million ($0.01/share) in the prior year quarter.
Working capital as of June 30, 2026 was $37.76 million.
Operating expenses for the year were $5.95 million, nearly flat year-over-year.
Income from investments rose to $1.01 million for the year, up from $0.79 million year-over-year.
Outlook and guidance
Updated Carangas PEA projects a post-tax NPV (5%) of $2.65 billion and IRR of 35.9% at base case prices.
Life of mine estimated at 19 years, producing 195 Moz silver, 1.1 Moz gold, 1,453 Mlbs zinc, and 941 Mlbs lead.
Initial capital costs projected at $644.5 million with a post-tax payback of 2.4 years.
Latest events from New Pacific Metals
- Advancing two world-class silver projects in Bolivia with robust economics and growth potential.NUAG
Corporate presentation - Silver Sand PFS filed with $740M NPV, net loss narrowed, and $25.9M raised in financing.NUAG
Q4 2024 - Carangas PEA projects $501M NPV, 26% IRR; net loss narrows to $1.26M on lower expenses.NUAG
Q1 2025 - Net loss improved, exploration spending continued, and Carangas PEA advanced amid ongoing risks.NUAG
Q2 2025 - Net loss improved, expenses declined, and Carangas PEA underscores both opportunity and risk.NUAG
Q3 2025 - Carangas PEA shows strong economics; net loss narrows and key projects gain legal, community support.NUAG
Q4 2025 - Net loss improved, major financing closed, and leadership finalized amid stable project spending.NUAG
Q1 2026 - Net loss increased, but lower expenses and Bolivia's reforms may boost future prospects.NUAG
Q2 2026 - Q3 net loss was $0.87M, with strong working capital and key project investments ongoing.NUAG
Q3 2026