Northern Minerals (NTU) H2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2026 earnings summary
29 Oct, 2026Executive summary
FY2026 focused on moving Browns Range from feasibility into FEED, project financing and construction readiness; a positive FID remains contingent on funding and Board approval.
The September 2025 DFS estimated A$592M pre-production capex and, under its Divergence Case, pre-tax real NPV8 of A$705M and IRR of 21%.
Browns Range is positioned as a potential non-China heavy rare earths supplier, with first production targeted for Q4 2028 subject to project funding.
Financial highlights
FY2026 total income was A$1.71M versus A$2.58M in FY2025; net loss widened to A$37.89M from A$27.37M.
Operating loss was A$37.37M; total expenses rose to A$39.08M from A$27.96M, including A$23.34M exploration and project evaluation expenditure.
Net operating cash outflow was A$29.19M versus A$25.80M; net investing outflow was A$24.77M versus A$0.47M, largely reflecting term deposits and site/head-office IT expenditure.
Cash and current term deposits totalled A$33.57M at 30 June 2026; net assets were A$20.97M versus A$1.69M a year earlier.
A$60.5M was raised before costs in November 2025; placement proceeds and existing cash funded project work and full repayment of the Iluka convertible note, including A$3.51M accrued interest.
Outlook and guidance
FID targeted for 30 September 2026 was not achieved; funding negotiations remain ongoing, with no legally binding project funding commitment obtained by the report date.
EXIM indicated it could consider debt financing of up to US$230M with EFA; both agencies’ support letters are conditional and non-binding, subject to due diligence, approvals and acceptable terms.
Subject to project funding, first concentrate production is targeted for Q4 2028; the pathway includes financial close, construction and commissioning.
Additional working-capital funding is needed to maintain planned activities; project construction funding is a separate, substantially larger requirement.
Latest events from Northern Minerals
- Construction approvals are complete; funding remains the gate to FID and Q1 2029 production.NTU
Q1 2027 TU - Advanced Browns Range Project targets FID in Q3 CY2026 and first production by Q4 CY2028.NTU
Q4 2026 TU - Browns Range targets FID by September 2026 to supply heavy rare earths by late 2028.NTU
Noosa Mining Conference 2026 - Advancing a high-grade rare earths project to supply critical materials for clean energy and electrification.NTU
Diggers and Dealers Mining Presentation - Net loss widened to $31.6M as Browns Range Project advanced, with major capital raised and DFS nearing completion.NTU
H2 2024 - Net loss increased to $16.0 million, with Browns Range DFS completed and major equity raised.NTU
H1 2026 - Browns Range advanced toward FID with major funding, exploration, and governance developments.NTU
Q2 2026 TU - DFS completed, funding secured, and Browns Range positioned for 2028 production.NTU
H2 2025 - Capital raised, project milestones achieved, and governance renewed amid market challenges.NTU
AGM 2024