Northern Minerals (NTU) H2 2026 earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Northern Minerals Limited

H2 2026 earnings summary

29 Oct, 2026

Executive summary

  • FY2026 focused on moving Browns Range from feasibility into FEED, project financing and construction readiness; a positive FID remains contingent on funding and Board approval.

  • The September 2025 DFS estimated A$592M pre-production capex and, under its Divergence Case, pre-tax real NPV8 of A$705M and IRR of 21%.

  • Browns Range is positioned as a potential non-China heavy rare earths supplier, with first production targeted for Q4 2028 subject to project funding.

Financial highlights

  • FY2026 total income was A$1.71M versus A$2.58M in FY2025; net loss widened to A$37.89M from A$27.37M.

  • Operating loss was A$37.37M; total expenses rose to A$39.08M from A$27.96M, including A$23.34M exploration and project evaluation expenditure.

  • Net operating cash outflow was A$29.19M versus A$25.80M; net investing outflow was A$24.77M versus A$0.47M, largely reflecting term deposits and site/head-office IT expenditure.

  • Cash and current term deposits totalled A$33.57M at 30 June 2026; net assets were A$20.97M versus A$1.69M a year earlier.

  • A$60.5M was raised before costs in November 2025; placement proceeds and existing cash funded project work and full repayment of the Iluka convertible note, including A$3.51M accrued interest.

Outlook and guidance

  • FID targeted for 30 September 2026 was not achieved; funding negotiations remain ongoing, with no legally binding project funding commitment obtained by the report date.

  • EXIM indicated it could consider debt financing of up to US$230M with EFA; both agencies’ support letters are conditional and non-binding, subject to due diligence, approvals and acceptable terms.

  • Subject to project funding, first concentrate production is targeted for Q4 2028; the pathway includes financial close, construction and commissioning.

  • Additional working-capital funding is needed to maintain planned activities; project construction funding is a separate, substantially larger requirement.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Northern Minerals