Logotype for NTPC Limited

NTPC (NTPC) Q4 11/12 earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for NTPC Limited

Q4 11/12 earnings summary

29 Oct, 2026

Executive summary

  • Record capacity addition of 2,820 MW in FY12 lifted installed capacity to 32,650 MW; including JVs and subsidiaries, capacity reached 37,014 MW at year-end and 39,174 MW after 2,160 MW commissioned in Q1 FY13.

  • Generation reached 222.07 BU; coal-station PLF was 85.0% versus India’s 73.32%, while grid restrictions and low demand constrained output.

  • Total standalone revenue rose 12.93% to ₹64,830.65 crore, while PAT increased 1.33% to ₹9,223.73 crore; proposed total dividend was ₹4 per share.

Financial highlights

  • Standalone revenue from operations was ₹62,052.23 crore versus ₹55,062.65 crore; total revenue was ₹64,830.65 crore versus ₹57,407.30 crore.

  • Standalone PBT rose to ₹12,326.16 crore from ₹12,049.60 crore; PAT was ₹9,223.73 crore versus ₹9,102.59 crore.

  • Consolidated revenue was ₹68,831.25 crore versus ₹60,008.18 crore; consolidated PBT was ₹13,137.26 crore and PAT ₹9,814.66 crore, versus ₹12,392.33 crore and ₹9,348.23 crore.

  • Fuel expense increased 18% to ₹41,635.46 crore; higher coal cost, imported coal mix and new-unit output contributed to the rise.

  • Adjusted for prior-year provision reversals and other prior-period items, generation, administration and other expenses were ₹3,588.79 crore, down 27% reported; FY11 included a ₹1,526.45 crore tariff provision.

Outlook and guidance

  • FY12–17 capacity-addition plan targets 14,038 MW, including 2,890 MW through JVs and subsidiaries; 12,941 MW was in bidding stages and feasibility reports covered 12,111 MW.

  • Projects under construction reached 16,638 MW after Q1 FY13 awards, including 4,210 MW through JVs; 12th Plan fuel was tied up, including captive mines expected to produce coal from the following year.

  • Long-term plan targets 128 GW of capacity by 2032; strategic expansion spans coal mining, hydro, nuclear, renewable energy and other parts of the power value chain.

  • Around 16,638 MW was under construction, and 6,860 MW of project work had been awarded during calendar 2012 at the shareholder letter date.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from NTPC