Project overview and resource expansion

  • Recently announced a Preliminary Economic Assessment (PEA) for a large gold resource, highlighting significant upside and ongoing aggressive drilling with five rigs active.

  • Two main deposits, Wenot (shear-hosted) and Gilt (intrusion-hosted), are only 450 m apart, with both showing mineralization to at least 1,200 m depth.

  • The project is located in Guyana, a favorable jurisdiction with strong government and community support for large-scale mining.

  • Infrastructure benefits from proximity to a major road, planned deepwater port, and potential hydropower and gas energy projects.

  • The site is a brownfield past producer with cleared land, existing warehouses, an airstrip, and a large tailings facility with expansion capacity.

Geology and deposit characteristics

  • Wenot is an open-pittable, shear-hosted deposit with 21 parallel zones, significant shallow resources, and a discovery cost of $4/oz.

  • Gilt is a 2.2 million ounce resource with subhorizontal zones, similar to Sigma-Lamaque in Quebec, and thick mineralized zones.

  • Drilling has confirmed mineralization at depth, with a recent deep hole intersecting seven gold zones 700 m below previous drilling.

  • Wenot's mineralization is hosted in a dike corridor and quartz feldspar porphyry, with wide, high-grade intersections well above the PEA cutoff.

  • The property has 2.5 km of Wenot shear drilled, with 4–5 km to the east and 1 km to the west remaining largely untested.

Economic assessment and production profile

  • PEA outlines a 6.3 million ounce production plan, targeting 350,000+ ounces/year over an 18-year mine life at 25,000–30,000 tpd.

  • Net present value (NPV) at 5% is $4 billion at $3,600/oz gold, with $8 billion cumulative cash flow and $1.4 billion initial CapEx.

  • At higher gold prices, NPV rises to $5.5 billion, IRR to 30%, and payback period is 3.4 years.

  • The open pit (Wenot) is a "super pit" (2.4 km x 1.1 km x 550 m), with a strip ratio of 6, and a starter pit in the west targeting higher grades.

  • Underground mining at Gilt uses drift and fill, with potential for blended mining to reduce costs; thick zones average 4,600 oz/vertical meter.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Omai Gold Mines