2 Aug, 2026Strategic growth vision and operational highlights
Aims to organically build into a 300 koz per annum gold producer, with a robust pipeline of projects and expansions underway.
FY26 saw record production of 141 koz, a 75% increase in resources, and a 159% increase in reserves year-to-date.
Approved construction of a new 3.0 Mtpa mill at Davyhurst, targeting a combined 4.2 Mtpa milling capacity by FY29.
Substantial liquidity of ~A$468 million, including A$267.7 million in cash and an undrawn A$200 million revolving credit facility.
FY27 production guidance is 125–140 koz at an AISC of A$3,400–A$3,600/oz, with A$425 million in capital investment planned.
Project pipeline and exploration
Key growth projects include Waihi Underground (approved), Round Dam Open Pit (PFS completed, FID expected 2H FY27), and ongoing expansion at Sand King and Riverina.
Exploration budget increased to A$75 million per year for the next three years, targeting resource and reserve growth and new mine discoveries.
Little Gem and Riverina trends continue to deliver high-grade drill results, with Little Gem’s maiden resource estimate targeted for 2Q FY27.
Round Dam PFS outlines an 8-year mine life with 724 koz mined at 1.7 g/t, and significant geological potential remains underexplored.
Mulline trend identified as a future high-grade exploration opportunity, with less than 5% of drill holes below 100m vertical depth.
Infrastructure and operational improvements
A$180 million allocated for infrastructure upgrades at Davyhurst, including accommodation, airstrip, haul roads, and on-site assay lab.
New mill construction underway, with commissioning expected in March quarter 2028, designed for operational flexibility and cost reduction.
Stockpile build to commence in 2Q FY27, with third-party milling to cease, supporting transition to in-house processing.
Operational flexibility enhanced by multiple mines and mills, reducing single asset risk and improving economies of scale.
Latest events from Ora Banda Mining
- Production set to double as new mill, mines, and exploration drive rapid growth.OBM
Diggers & Dealers Mining Forum 20264 Aug 2026 - Doubling output and new mill drive growth to 300,000 ounces by FY 2029, backed by strong finances.OBM
Noosa Mining Conference 202623 Jul 2026 - Record production, robust cash flow, and major resource growth drive multi-year expansion.OBM
Q4 2026 TU15 Jul 2026 - Record gold output and profit surge as underground expansion drives strong financials.OBM
H1 202511 Jun 2026 - Record revenue and profit growth driven by higher gold prices and increased production.OBM
H1 202611 Jun 2026 - Record gold output and cash flow, with higher AISC and strong cash reserves.OBM
Q3 2026 TU15 Apr 2026 - Record gold output and profit, strong cash flow, and major growth investment set up FY26 expansion.OBM
H2 20251 Apr 2026 - Record gold output, lower costs, and strong growth outlook following underground transition.OBM
H2 20241 Apr 2026 - Record gold output and robust cash growth offset higher costs from expanded third-party processing.OBM
Q2 2026 TU28 Jan 2026