Revenue reached USD 1,468.4 million, EBITDA USD 108.3 million, and net profit attributable to shareholders USD 53.4 million, up 73.2%, 100.2%, and 112.7% year-over-year, respectively.
Consolidated backlog reached USD 9.4 billion, up 7.5% year-over-year; pro forma backlog including BESIX was USD 13.1 billion.
New awards totaled USD 1.9 billion consolidated and USD 2.2 billion pro forma with BESIX, across infrastructure, commercial, and data center projects.
U.S. business recorded USD 2.9 billion in backlog and 343.7% year-over-year EBITDA growth, driven by data centers and specialized sectors.
Advanced projects included U.S. data centers, Saudi industrial wastewater treatment, and Egyptian wind power.
Financial highlights
Gross profit rose to USD 147.2 million from USD 91.8 million, and operating profit more than doubled to USD 98.1 million from USD 45.6 million year-over-year.
Finance income was USD 53.2 million and finance costs were USD 66.7 million.
Operating cash flow improved to USD 26.2 million from USD 14.1 million year-over-year; quarter-end cash and cash equivalents were USD 1,205.9 million.
EBITDA margin increased to 7.4% from 6.4%; net profit margin rose to 3.6% from 3.0%.
Pro forma EBITDA including BESIX grew 68.8% to USD 117.3 million; BESIX contributed USD 4.9 million to net profit, up 48.5%.
Outlook and guidance
Focus remains on disciplined project execution and cost control amid uncertain market conditions.
2026 outlook remains optimistic based on backlog quality and expected bottom-line performance, subject to potential force majeure impacts.
Continued expansion in U.S. data centers and specialized markets, including aviation and advanced manufacturing; further backlog growth, if any, is expected from U.S. data centers.
Concessions platform development and regional expansion of building materials and facility management businesses remain priorities.
Latest events from Orascom Construction
- Merger aims to scale infrastructure investment, with cash deployment targeted within 18-24 months.ORAS
Investor update - Adjusted EBITDA rose 29.4% as backlog reached $7.7bn.ORAS
H1 2024 - Adjusted earnings rose as consolidated backlog hit $8.0bn, despite lower awards.ORAS
Q3 2024 - Adjusted EBITDA rose 13.3%, with $7.6B backlog and a 5% 2025 margin target.ORAS
H2 2024 - Revenue and EBITDA grew as backlog reached $8.7B, despite lower reported profit.ORAS
Q1 2025 - H1 revenue grew 32.4%, backlog hit $9.6bn and Egypt’s 650 MW wind farm began operations.ORAS
H1 2025 - Revenue rose 47.8%, with $3.7 billion in awards and an $8.6 billion backlog.ORAS
Q3 2025 - Record backlog, 65% net income growth, and major wind project expansion in FY 2025.ORAS
H2 2025 - H1 revenue rose 52.3%, net profit 90.0% and backlog reached USD 10.9B.ORAS
H1 2026