Peninsula Energy (PEN) H1 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H1 2026 earnings summary
15 Mar, 2026Executive summary
Operations at the Lance Uranium Project in Wyoming recommenced with low pH ISR, and the Phase II expansion of the Central Processing Plant (CPP) was completed, making the company a fully independent producer of dried yellowcake.
A Reset Plan was implemented in August 2025, reducing production guidance due to commissioning delays and lower-than-expected wellfield performance, and the Life of Mine plan was withdrawn pending new data.
Safety performance remained strong with no Lost Time Injuries, though there was a slight increase in the Total Recordable Injury Frequency Rate to 3.89.
Board renewal was completed with new appointments and retirements, and the company continued to focus on wellfield development and resource upgrades.
Financial highlights
Net loss for the half-year ended 31 December 2025 was US$15.3 million, compared to a loss of US$7.7 million for the same period last year, mainly due to an US$8.4 million inventory write-down.
Cash and cash equivalents increased to US$31.8 million from US$9.2 million at 30 June 2025, following a successful A$69.9 million equity raise and full drawdown of a US$12.6 million convertible debt facility.
Net assets rose to US$203.2 million from US$170.1 million at 30 June 2025.
No uranium sales occurred during the half-year; five of six legacy sales contracts were terminated, with a US$5.0 million termination payment made.
Outlook and guidance
The Reset Plan provides a more risk-adjusted production and expenditure outlook through December 2027, with a focus on improved wellfield design and operational performance at MU-4.
Early acidification and uranium head grades at MU-4 are exceeding expectations, supporting confidence in future production targets.
Additional funding may be required if operational or market conditions deviate from the Reset Plan.
Latest events from Peninsula Energy
- Lance Project ramp-up advances, with robust funding and improved production outlook for 2026.PEN
Q2 2026 TU15 Mar 2026 - Transition to uranium production on track, with first sales expected by mid-2025.PEN
AGM 202413 Jan 2026 - First yellowcake production and major funding secure ramp-up for US uranium supply growth.PEN
Q1 2026 TU21 Dec 2025 - Production resumes with reset contracts, full funding, and strong growth targets for 2025–2027.PEN
Investor Update23 Nov 2025 - Shareholders approved multiple share issues and incentives, with strong proxy support.PEN
EGM 202530 Sep 2025 - Restarted uranium production, restructured contracts, and secured funding amid operational challenges.PEN
H2 202530 Sep 2025 - Lance Project advances toward full-scale uranium production with strong resources and funding.PEN
Investor Presentation22 Aug 2025 - Production ramp-up advances with new financing, but contract terminations heighten spot price risk.PEN
Q4 2025 TU3 Aug 2025 - Lance uranium project advances toward production with strong resources, cash, and growth upside.PEN
Corporate Presentation30 Jun 2025