Pensana (PRE) H2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2026 earnings summary
27 Oct, 2026Executive summary
FY2026 advanced Longonjo construction and procurement, but delayed Cascade funding slowed work and pushed expected first production to late 2028.
Longonjo targets initial output of 20,000tpa MREC, rising to 40,000tpa from year four; heavy rare earth recovery studies target up to 122tpa of dysprosium and terbium products.
Financial highlights
Total loss after tax was US$14.1m (FY2025: US$11.5m); total comprehensive loss was US$17.0m (FY2025: US$5.9m).
Cash and cash equivalents were US$5.65m at 30 June 2026 (FY2025: US$0.81m); net assets rose to US$100.3m from US$50.5m.
Financing activities generated US$54.8m; cash spent on Longonjo property, plant and equipment was US$35.4m, versus US$5.8m in FY2025.
FY2026 included a US$5.92m impairment charge for Saltend assets and a US$2.99m foreign-exchange gain, versus a US$4.61m FX loss in FY2025.
Outlook and guidance
First MREC production is targeted for late 2028; Phase 1 plans ~20,000tpa, with expansion to ~40,000tpa from the fourth operating year.
Construction and commissioning depend on funding. Detailed design, higher-cost site work and long-lead procurement were scaled back pending financing finalisation.
Priorities include completing engineering and procurement, advancing construction, expanding resource drilling and developing heavy rare earth recovery and downstream separation and metallisation.
Latest events from Pensana
- Large-scale rare earth mine targets 2027 production, securing global partnerships and offtakes.PRE
Corporate presentation - U.S.-backed rare earth supply chain to launch in 2027, targeting EV and defense markets.PRE
Corporate presentation - Longonjo targets billion-tonne rare earth resource, enabling a U.S. mine-to-magnet supply chain.PRE
Corporate presentation - Losses increased as Longonjo advanced, with funding and going concern risks persisting.PRE
H2 2024 - $268M financing secured for Longonjo enables main construction; loss narrows, funding risks remain.PRE
H1 2025 - Longonjo construction advances with full funding, strategic partnerships, and robust ESG progress.PRE
H2 2025 - Longonjo mine construction accelerates with robust funding, resource growth, and strong market demand.PRE
H1 2026