Perpetua Resources (PPTA) Q4 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2025 earnings summary
31 Mar, 2026Executive summary
The Stibnite Gold Project is a large-scale, open-pit gold, silver, and antimony mine in Idaho, designed to redevelop a brownfield site and restore legacy environmental impacts. The project is expected to be one of the largest and highest-grade gold mines in the U.S. and a major domestic antimony producer. Key 2025 milestones include receipt of all major federal permits, commencement of early works construction, and significant progress in engineering, contracting, and project financing.
Financial highlights
Life-of-mine (15 years) production: 4.22 Moz gold, 106 Mlbs antimony, 1.16 Moz silver.
Initial capital cost: $2.58 billion, with sustaining and closure capital bringing total to $3.41 billion.
Life-of-mine average cash costs: $581/oz Au (net of by-product credits); AISC: $833/oz Au.
After-tax NPV (5%): $3.46 billion; after-tax IRR: 23.5%; payback: 2.4 years (base case: $3,250/oz Au, $10/lb Sb, $40/oz Ag).
2025 net loss: $100.4 million (2024: $14.5 million), driven by $121.3 million in exploration and pre-development expenses and a $22.4 million decrease in grant income.
Cash and cash equivalents at year-end: $714.2 million; restricted cash: $59.5 million.
$862 million raised in equity offerings in 2025; $2.7 billion U.S. EXIM loan in final approval process.
Outlook and guidance
Focus for 2026: secure final project financing, complete remaining state permits, advance to full construction, expand management and workforce, and progress antimony offtake agreements.
Anticipates final U.S. EXIM loan approval in 2H 2026; expects sufficient liquidity to fund activities until full project sanction.
Latest events from Perpetua Resources
- Largest U.S. gold reserve and only antimony source fully funded, permitted, and set for 2029 start.PPTA
Status Update6 Jan 2026 - Annual meeting to elect directors, ratify auditors, and review strong governance and ESG practices.PPTA
Proxy Filing2 Dec 2025 - AGM to elect directors and ratify auditors, with virtual voting by May 13, 2025.PPTA
Proxy Filing2 Dec 2025 - $807M equity raised, construction started, and $2B debt financing pursued amid ongoing risks.PPTA
Q3 202517 Nov 2025 - Q2 net loss fell to $3.7M; $34.4M DPA funding secured, but liquidity risk persists.PPTA
Q2 202410 Nov 2025 - Permitting and construction readiness advanced, but liquidity and funding risks persist.PPTA
Q3 202410 Nov 2025 - Q1 2025 net loss widened; key milestones achieved but liquidity risks persist.PPTA
Q1 202510 Nov 2025 - Secured all federal permits and $474M equity, but full project funding and permitting risks remain.PPTA
Q2 202510 Nov 2025 - Secured major funding and permitting milestones for a leading U.S. gold-antimony project.PPTA
Q4 202410 Nov 2025