Logotype for PMET Resources Inc

PMET Resources (PMET) Study update summary

Event summary combining transcript, slides, and related documents.

Logotype for PMET Resources Inc

Study update summary

11 Nov, 2026

Study economics

  • After-tax NPV at 8% is ~CA$5.10B (US$3.72B) and IRR 40.4% at US$1,788/t SC5.5; at US$1,400/t SC5.5, after-tax NPV is ~CA$3.29B.

  • Pre-tax NPV at 8% rose to CA$8.5B from CA$2.5B, pre-tax IRR to 47.2% from 19.9%, and payback shortened to 2.6 years from 4.9.

  • LOM FOB Québec costs are CA$594/t cash operating and CA$657/t AISC, net of tantalum credits, down 19% and 18%; site cash operating costs are $212/t and AISC $480/t of concentrate.

  • Tantalum adds a $108/t cost credit at the study price of $120/lb contained tantalite; OPEX fell ~20% versus the prior study while phase-one and phase-two CAPEX remained broadly in line.

Development plan and production

  • Phase 1 combines underground-first Nova Zone mining with a 2.2 Mtpa DMS plant; phase 2 adds a 2.9 Mtpa train and open-pit mining, raising capacity to 5.1 Mtpa and spodumene output to ~800,000 tpa over a ~20-year mine life.

  • Phase 1 targets up to ~560,000 tpa spodumene in its first three production years and up to ~455,000 lb/year contained Ta₂O₅; mine-life average tantalite output is ~635,000 lb/year.

  • Phase 1 capital is CA$1,391M (CA$1,080M net of anticipated pre-production and tax credits); phase 2 capital is CA$672M (CA$595M net of anticipated tax credits).

  • The maiden Probable Mineral Reserve is 83.0 Mt at 1.27% Li₂O and 148 ppm Ta₂O₅, containing 2.61 Mt LCE and 12.3 kt Ta₂O₅.

  • A starter pit supplies ~700,000 tonnes in year one with a 60 m lake setback; a simplified single-stage DMS flow sheet removes regrind and secondary DMS recovery systems.

Project execution and next steps

  • FID remains targeted for late 2027, subject to approvals and financing; DMS commissioning is targeted for late 2029 and commercial production for end-Q1 2030.

  • Mine authorization, detailed engineering, process testwork, financing and Cree IBA discussions are progressing; the Cree Nation of Chisasibi letter of intent frames work toward an IBA.

  • A CV5/CV13 PEA was expected before year-end 2026 to assess lithium, caesium and tantalum opportunities; CV13 may contribute to phase 2 and extend mine life.

  • Bulk sampling is intended to de-risk operations and support customer engagement but is not required for FID; CEO recruitment is underway, with Ken Brinsden expected to transition to executive chair and later non-executive chair.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from PMET Resources