Predictive Discovery (PDI) Investor Update summary
Event summary combining transcript, slides, and related documents.
Investor Update summary
8 Jul, 2026Project overview and highlights
Bankan Gold Project is one of Africa's largest and most advanced gold projects, with a 12.2-year mine life and average annual production of ~250,000 ounces at an all-in sustaining cost (AISC) of US$1,057/oz.
Mineral resource is 5.5Moz with a 3Moz ore reserve, and total gold production is projected at 3.03Moz from 54.5Mt at 1.86g/t Au, with 92.8% recovery.
Project NPV5% is US$1.6bn at US$2,400/oz gold price, with IRR of 46% and payback under 2 years; at US$3,300/oz, NPV5% rises to US$2.9bn and IRR to 73%.
Each US$100/oz increase in gold price adds ~US$140m to NPV.
Environmental Compliance Certificate and ESIA approved in January 2025; exploitation permit application is in its final stage.
Mining, processing, and infrastructure
Mining strategy includes three open pits (NEB, GBE, BC) and NEB underground, with early underground development to access high-grade ore.
Open pit strip ratio reduced to 1.9:1 due to steeper wall angles and smaller NEB pit; underground mining uses hybrid long hole open stoping with paste fill.
Processing plant capacity is 4.5Mtpa, using conventional CIL with gravity recovery; average gold recovery is 92.8%, with 32% recovered through gravity circuit.
Power supplied by a 32.5MW HFO plant and 30MWp solar farm; water sourced from dewatering bores and TSF.
Filtered tailings storage facility (TSF) with HDPE lining and zero-discharge design, plus comprehensive surface water and sediment control.
Financial metrics and sensitivities
Pre-production capital cost is US$463m, with sustaining capital of US$208.6m and closure costs of US$39.6m.
Project expected to generate >US$250m average annual free cash flow at US$2,400/oz, rising to >US$400m at US$3,300/oz.
Payback period is less than two years at US$2,400/oz, and just over one year at US$3,300/oz.
Project economics are robust to changes in key assumptions, with strong leverage to gold price.
All-in sustaining cost reduced by $100/oz compared to PFS, mainly due to higher feed grade and optimized mining.
Latest events from Predictive Discovery
- Kiniéro ramp-up and Robex merger drove record gold output, revenue, and cash flow.PDI
Q3 202628 Apr 2026 - Bankan Gold Project advanced with major milestones, robust funding, and strong project economics.PDI
H2 20241 Apr 2026 - Bankan Gold Project advanced with DFS, ESIA, A$69m raise, and Robex merger; net assets up 35%.PDI
H2 20251 Apr 2026 - Net loss increased to $12.9M as Bankan project advances and Robex merger nears completion.PDI
H1 20265 Mar 2026 - Gold project in Guinea nears permit approval, targeting mid-2028 production and strong returns.PDI
2025 Precious Metals Summit - Beaver Creek3 Feb 2026 - Merger with Robex creates a major West African gold producer, advancing Bankan Project.PDI
Q2 2026 TU28 Jan 2026 - Merger forms Guinea's largest gold producer, targeting 400,000+ oz/year and 9Moz+ resources by 2029.PDI
M&A Announcement14 Dec 2025 - Set to produce 250,000 oz/year at low cost, with strong growth and ESG focus in Guinea.PDI
Noosa Mining Investor Conference16 Nov 2025 - Merger with Robex forms a major West African gold producer, de-risking Bankan Project funding.PDI
Q1 2026 TU29 Oct 2025